RDP Community MP MPA Provincial Government CRISP RWASH Other
Name:
Ale Kindergarten Classroom
GPS Coordinates:
-9.04639(lat), 159.10967897(lng)
Province:
Central
Ward:
Pavuvu
Village:
Ale
Cycle:
Cycle6
Nature of Sub-project:
New
-
-
-
Subproject Objective:
To construct a permanent kindy classroom for students/children. This will provide teachers and students a good and comfortable environment to increase human resources for our country.
Brief Description:
To construct a good and conclusive learning environment for our young children within our catchment areas. The community is well prepared to contribute local materials like gravel, sand, trees for timber and unskilled labors. Our community required RDP for funding support in terms of hardware materials, skilled labor & technical experts to complete the project.
Date approved by Province:
16/03/2018
Date TDF approved:
23/10/2018
Community Helper name:
John Baptist Tura
Is this project added because of a discontinued project:
No
Subproject Type:
Classroom
Sector:
Education
Subsector:
Pre-primary Education
Date of SIC establishment meeting:
26/10/2018
Agreed name of SIC:
Ale Kindy SIC
SIC Executive Members:
Position (given)
Name
Gender M/F (select)
Chairperson
Desmond Ngaobua
Male
Treasurer/Accountant
Abraham Maewe
Male
Secretary
Gloria Faelo
Female
Technical Officer
Hudson Matevaka
Male
Youth Member
Diana Afemako
Female
Member1
Milton Koti
Male
Member2
Christin Sepo
Female
Member3
Pamela Taiho
Female
Total Beneficiaries
Age Group
Male
Female
Total
0 - 14 yrs
83
84
167
15 - 24 yrs
77
74
151
25 - 59 yrs
102
96
198
60+ yrs
14
10
24
Total
276
264
540
People with special needs:
13
Households:
65
Names of villages expected to benefit and number of beneficiaries:
Ale
Age Group
Male
Female
Total
0 - 14 yrs
24
26
50
15 - 24 yrs
25
26
51
25 - 59 yrs
32
30
62
60+
4
3
7
Total
85
85
170
People with special needs
3
Households
21
Pepesala
Age Group
Male
Female
Total
0 - 14 yrs
8
7
15
15 - 24 yrs
6
5
11
25 - 59 yrs
9
9
18
60+
2
1
3
Total
25
22
47
People with special needs
2
Households
7
Point 6
Age Group
Male
Female
Total
0 - 14 yrs
40
39
79
15 - 24 yrs
38
36
74
25 - 59 yrs
48
45
93
60+
5
4
9
Total
131
124
255
People with special needs
5
Households
27
Maone
Age Group
Male
Female
Total
0 - 14 yrs
11
12
23
15 - 24 yrs
8
7
15
25 - 59 yrs
13
12
25
60+
3
2
5
Total
35
33
68
People with special needs
3
Households
10
Work plan stages and activities:
Stage1
Completed
Site development and construction of storage shed
Yes
Collect sand & gravel
Yes
Timber milling & timber carrying
Yes
Procurement of hardware materials & transportation