Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

The objective of this programme is to improve access to basic services in rural areas
and the production and productivity of farmers.

Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

Vura Classroom Building

Print

latest report image

Status: Ongoing
86.7%
0%

86.7% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Vura Classroom Building
GPS Coordinates: -9.018406(lat), 160.20800769(lng)
Province: Central
Ward: East gela
Village: Vura
Cycle: Cycle6
Nature of Sub-project: New

-
-
-

Subproject Objective: To construct a permanent classroom building to improve learning for students and staff.

Brief Description: To construct a good and conclusive permanent classroom building for staff and students. This will help staffs and all students in their learning for future human resources. Our community required RDP for funding support in terms of hardware materials, skilled labor & technical experts to complete the project.

Date approved by Province: 16/03/2018
Date TDF approved: 27/11/2018
Community Helper name: Clement Roy

Is this project added because of a discontinued project: No

Subproject Type: Classroom
Sector: Education
Subsector: Primary Education

Date of SIC establishment meeting: 07/12/2018
Agreed name of SIC: Vura Classroom SIC

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson John Leta Male
Treasurer/Accountant Sam Sogala Male
Secretary David Kaoni Male
Technical Officer George Sasi Male
Youth Member
Member1
Member2
Member3

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 30 29 59
15 - 24 yrs 45 54 99
25 - 59 yrs 76 78 154
60+ yrs 7 0 7
Total 158 161 319
People with special needs: 2 Households: 77


Names of villages expected to benefit and number of beneficiaries:

Vura

Age Group Male Female Total
0 - 14 yrs 30 29 59
15 - 24 yrs 45 54 99
25 - 59 yrs 76 78 154
60+ 7 0 7
Total 158 161 319
People with special needs 2 Households 77

Work plan stages and activities:

Stage1 Completed
Site development and construction of storage shed Yes
Collect sand & gravel Yes
Timber milling & timber carrying Yes
Procurement of hardware materials & transportationp Yes
Profiling & excavation of trenches & footing Yes
Stage2 Completed
Reinforce deformation and casing preparation for post Yes
Pouring concrete to footing & post block laying & septic concrete flooring and excavation Yes
Fixing of bearers and floor joist Yes
Preparation and fixing of wall panels Yes
Fixing of roof structure and roof cladding Yes
Stage3 Completed
Floor lining and external wall cladding Yes
Ceiling noggins, ceiling and internal wall lining Yes
Fixing of door and window frames & installation Yes
Construction of Toilet/shower room, septic and soak part No
Cleaning, landscaping and others No

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $
1 Building Supervisor (10%) Unknown Work 2000
2 Milling Unknown Work 13000
3 Mobilization Unknown Work 25850
4 Hardware Materials Unknown Goods 118480
5 Building Supervisor (40%) Unknown Work 8000
6 Hardware Materials Unknown Goods 22670
7 Building Supervisor (40%) Unknown Work 8000
8 Building Supervisor (10%) Unknown Work 2000

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan:

Operation and Maintenance Monitoring Report: