Subproject Objective:
To construct a permanent classroom building to improve learning for students and staff.
Brief Description:
To construct a good and conclusive permanent classroom building for staff and students. This will help staffs and all students in their learning for future human resources. Our community required RDP for funding support in terms of hardware materials, skilled labor & technical experts to complete the project.
Date approved by Province:
16/03/2018
Date TDF approved:
27/11/2018
Community Helper name:
Clement Roy
Is this project added because of a discontinued project:
No
Subproject Type:
Classroom
Sector:
Education
Subsector:
Primary Education
Date of SIC establishment meeting:
07/12/2018
Agreed name of SIC:
Vura Classroom SIC
SIC Executive Members:
Position (given)
Name
Gender M/F (select)
Chairperson
John Leta
Male
Treasurer/Accountant
Sam Sogala
Male
Secretary
David Kaoni
Male
Technical Officer
George Sasi
Male
Youth Member
Member1
Member2
Member3
Total Beneficiaries
Age Group
Male
Female
Total
0 - 14 yrs
30
29
59
15 - 24 yrs
45
54
99
25 - 59 yrs
76
78
154
60+ yrs
7
0
7
Total
158
161
319
People with special needs:
2
Households:
77
Names of villages expected to benefit and number of beneficiaries:
Vura
Age Group
Male
Female
Total
0 - 14 yrs
30
29
59
15 - 24 yrs
45
54
99
25 - 59 yrs
76
78
154
60+
7
0
7
Total
158
161
319
People with special needs
2
Households
77
Work plan stages and activities:
Stage1
Completed
Site development and construction of storage shed
Yes
Collect sand & gravel
Yes
Timber milling & timber carrying
Yes
Procurement of hardware materials & transportationp
Yes
Profiling & excavation of trenches & footing
Yes
Stage2
Completed
Reinforce deformation and casing preparation for post
Yes
Pouring concrete to footing & post block laying & septic concrete flooring and excavation
Yes
Fixing of bearers and floor joist
Yes
Preparation and fixing of wall panels
Yes
Fixing of roof structure and roof cladding
Yes
Stage3
Completed
Floor lining and external wall cladding
Yes
Ceiling noggins, ceiling and internal wall lining
Yes
Fixing of door and window frames & installation
Yes
Construction of Toilet/shower room, septic and soak part
No
Cleaning, landscaping and others
No
Community procurement plan. List of up to 20 items/contracts: