latest report image

Status: Ongoing
73.3%
13.3%

86.7% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Yandina CHS Library
GPS Coordinates: -9.086865(lat), 159.225145(lng)
Province: Central
Ward: Banika
Village: Yandina
Cycle: Cycle6
Nature of Sub-project:

-
-
-

Subproject Objective: To construct a permanent School Library Building to assist students in their research accessibility as part of their learning.

Brief Description: To construct a concrete low cost building that will accommodate two blocks, one for Library and the other for toilet. The school and community will provide local materials, such as timber, gravel and sand as part of their community contribution for the successful completion of the highly needed school infrastructure.

Date approved by Province: 16/03/2018
Date TDF approved: 16/10/2018
Community Helper name: John Batist Tura

Is this project added because of a discontinued project: No

Subproject Type: Classroom
Sector: Education
Subsector: Upper-secondary Education

Date of SIC establishment meeting: 21/10/2018
Agreed name of SIC: Yandina CHS Library SIC

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson Noel Hulanga Male
Treasurer/Accountant Fisher Young Lulu Male
Secretary Gwen Isulia Female
Technical Officer Andrew Faeni Male
Youth Member Jimmy Korowane Male
Member1 Andrew Faeni Male
Member2 May Kena Female
Member3 Aida Talent Female

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 637 648 1285
15 - 24 yrs 534 518 1052
25 - 59 yrs 678 654 1332
60+ yrs 259 239 498
Total 2108 2059 4167
People with special needs: 88 Households: 798


Names of villages expected to benefit and number of beneficiaries:

Yandina

Age Group Male Female Total
0 - 14 yrs 347 344 691
15 - 24 yrs 398 390 788
25 - 59 yrs 430 420 850
60+ 195 178 373
Total 1370 1332 2702
People with special needs 65 Households 595

Leufoman

Age Group Male Female Total
0 - 14 yrs 25 12 37
15 - 24 yrs 5 9 14
25 - 59 yrs 9 9 18
60+ 1 3 4
Total 40 33 73
People with special needs 2 Households 10

Moe

Age Group Male Female Total
0 - 14 yrs 36 57 93
15 - 24 yrs 21 15 36
25 - 59 yrs 35 37 72
60+ 4 2 6
Total 96 111 207
People with special needs 4 Households 21

Hae

Age Group Male Female Total
0 - 14 yrs 39 43 82
15 - 24 yrs 25 32 57
25 - 59 yrs 56 56 112
60+ 6 0 6
Total 126 131 257
People with special needs 5 Households 45

Louna

Age Group Male Female Total
0 - 14 yrs 173 171 344
15 - 24 yrs 73 57 130
25 - 59 yrs 130 116 246
60+ 49 53 102
Total 425 397 822
People with special needs 12 Households 107

Laola

Age Group Male Female Total
0 - 14 yrs 17 21 38
15 - 24 yrs 12 15 27
25 - 59 yrs 18 16 34
60+ 4 3 7
Total 51 55 106
People with special needs 0 Households 20

Work plan stages and activities:

Stage1 Completed
Site development and construction of storage shed Yes
Collect sand & gravel Yes
Timber milling Yes
Procurement of hardware materials & transportation Yes
Profiling & excavation of trenches & footings Yes
Stage2 Completed
Concrete slabbing and block laying Yes
Block laying and septic concrete flooring and excavation Yes
Construction of roofing framing Yes
Roof cladding and ridge capping and fascia board fixing Yes
Ceiling noggings and linning Yes
Stage3 Completed
Construction of window frame and toilet piping Yes
Painting and finishing Yes
Cleaning and land scaping No
Others if any No
100% of RDP funds acquitted by SIC and sent to PCU for audit Yes

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $
1 Building Supervisor Unknown Work 2000
2 Milling Unknown Work 8400
3 Mobilization Unknown Work 28158
4 Hardware Materials Unknown Goods 121842
5 Building supervisor Unknown Work 8000
6 Hardware Materials Unknown Goods 21600
7 Building Supervisor Unknown Work 8000
8 Building Supervisor Unknown Work 2000

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan: