Solomon Islands Ministry of Development, Planning and Aid Coordination
<% completition_percent %>% Completion
<% work_stage.stage %> | Completed |
---|---|
<% work_activity.description %> |
|
Issue | Date Created | Date Updated | Resolved Y/N |
---|---|---|---|
Due to misunderstanding between the supervisor and the community that hold the progress of the subproject. | 22/06/2019 | 22/06/2019 | Yes |
flooding due to bad weather bury pipe trench connecting spring box to generator pump thus slow down progress inorder to test run the pump system. | 22/11/2019 | 22/11/2019 | No |