Kagua Water Supply / Monitoring Report / 05/06/2018 05:56

<% completition_percent %>% Completion


Date of monitoring visit: 30/05/2018
Keliv Sangoihenua

Work plan stages and activities:

<% work_stage.stage %> Completed
<% work_activity.description %> Yes Yes No

Implementation Problem or Procurement issues:

Issue Date Created Date Updated Resolved Y/N
Delay of ship boat travelling to SP site has slow moving of SP's materials to site which should allow other major works to start. 31/05/2018 05/06/2018 No
With slow process to get RWASH contribution for procurement as schedule also force SIC to used few savings from its RDP tranche to meet other pipings so to avoid frustration among community members. 07/05/2018 05/06/2018 No

Are Financial records being kept up to date: Yes

Have records of community contributions been updated: Yes

Are there any changes to other contributions? Yes

SIC has able to secure support from Renbel Constituency/ MP for assisting transporting SP's materials to site via its MV Avaikimaine which still reschedule to leave by 7th June 2018. As per estimated freight cost in the BOQ value to $10,000.00. With support by MP, the amounts will use for additional pipes (stand pipes + branch line piping) and also to add towards hiring or engaging of technical supervisor. A possible co-funding is expected from RWASH which will meet other complemented components of the SP as per TDF. Its value to around $65,000.00. Major part of it is to meet cost for construction of 2 x standalone rainwater catchments (3000ltrs).


Other Comment: Todate, major procurement under RDP funds has been done and ready for shipments to SP's site. Consultation with RWASH extension team in the Province for conduction of pre-construction workshop which will reflect huge corporation and efforts in implementation of such policy lines. Other arrangements to engage technical specialize person to supervise the construction of the water supply is in good progress and SIC to confirm that while all materials are on site. Other negotiations are in good progress to engage an excavator machine from Logging & mining companies operated in the island (Rennell) to do excavation for main pipe lines. Again, successful completion of this SP will set a good precedence and landmark for RDP doing similar SPs in future.