Kagua Water Supply / Monitoring Report / 28/09/2018 05:07

<% completition_percent %>% Completion


Date of monitoring visit: 28/08/2018
Keliv Sangoihenua

Work plan stages and activities:

<% work_stage.stage %> Completed
<% work_activity.description %> Yes Yes No

Implementation Problem or Procurement issues:

Issue Date Created Date Updated Resolved Y/N
Delay of ship boat travelling to SP site has slow moving of SP's materials to site which should allow other major works to start. 31/05/2018 28/09/2018 Yes
With slow process to get RWASH contribution for procurement as schedule also force SIC to used few savings from its RDP tranche to meet other pipings so to avoid frustration among community members. 07/05/2018 05/06/2018 No

Are Financial records being kept up to date: Yes

Have records of community contributions been updated: Yes

Are there any changes to other contributions? Yes

The likely co-funding arrangement with SI RWASH has been push back due to slow processes or delay of firm assurance.


Other Comment: The implementation of the SP has been in very encouraging phase. The community is so supportive and its something the SIC should be continue to upkeep through to the completion. Regular presence of PSU is highly require so can continue to give motivation for speedy work of the SP. The hired contractor is work so hard even though he is not responsible for the whole SP work. The community is manning the rehab works on the storage and the pump shed which is expected to complete by early October, 2018. 1 x 150m roll of 50mm is still remain and should be used for further extension as per technically require. There were some missing parts on fittings as reported to PCU engineer but were able to replace from others which has extra. PSU will continue to closely monitor as matter of time for completion.