Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

The objective of this programme is to improve access to basic services in rural areas
and the production and productivity of farmers.

Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

Lale Kindergarten

Print

latest report image

Status: Completed
92.3%
7.7%

100% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Lale Kindergarten
GPS Coordinates: -8.173167000000(lat), 156.581100000000(lng)
Province: Western
Ward: South ranongga
Village: Lale
Cycle: Cycle5
Nature of Sub-project: New

-
-
-

Subproject Objective: To provide infrastructure for community to facilitate standard building required for Early Childhood Education.

Brief Description: Lale is a big community that supply school kids to primary school level. Lale itself is located at south Ranoggga . Lale does not provide early childhood classes for children to begin their learning even though they have a plan to do so. At the present all children wait to reach certain age to begin their primary level of education.

Date approved by Province: 03/12/2015
Date TDF approved: 31/05/2016
Community Helper name: Bily Agolo

Is this project added because of a discontinued project: No

Subproject Type: Classroom
Sector: Education
Subsector: Pre-primary Education

Date of SIC establishment meeting: 05/01/2016
Agreed name of SIC: Lale Kindergarten SIC

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson Joel Panda Male
Treasurer/Accountant Glender Towken Female
Technical Officer Grendley Dodi Male
Secretary Francis Tekulu Male
Member1 Medana Jino Male
Member2 Jiudy Levani Female
Member3 Jacob Zinihite Male
Youth Members Geilyn Deme Female

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 97 124 221
15 - 24 yrs 110 103 213
25 - 59 yrs 140 143 283
60+ yrs 49 32 81
Total 396 402 798
People with special needs: 19 Households: 167


Names of villages expected to benefit and number of beneficiaries:

Lale

Age Group Male Female Total
0 - 14 yrs 78 112 190
15 - 24 yrs 101 92 193
25 - 59 yrs 127 131 258
60+ 45 31 76
Total 351 366 717
People with special needs 15 Households 152

Ngaidavala

Age Group Male Female Total
0 - 14 yrs 19 12 31
15 - 24 yrs 9 11 20
25 - 59 yrs 13 12 25
60+ 4 1 5
Total 45 36 81
People with special needs 4 Households 15

Work plan stages and activities:

Stage1 Completed
Mobilisation of resources, site developement and construction/identification of storage shed Yes
Collection of sand , gravel and site clearance Yes
Procurement of hardware materials Yes
Timber milling and seasoning Yes
Set up layout Yes
Stage2 Completed
Construction of post, profiling Yes
Bearer, floor joist, bottom plate and stud Yes
Construction of roof, rufter, purlin & ridge board Yes
Roof cladding & fixing Yes
Stage3 Completed
Wall cladding, flooring Yes
Fixing of doors, windows, toilet Yes
Painting and finishing touches Yes
Cleaning and chart away of rubbish Yes

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $
1 Hardware Materials unknown Goods 182953.5

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan:

Operation and Maintenance Monitoring Report: