Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

The objective of this programme is to improve access to basic services in rural areas
and the production and productivity of farmers.

Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

Zutapati Water Supply

Print

latest report image

Status: Ongoing
55.6%
11.1%

66.7% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Zutapati Water Supply
GPS Coordinates: -7.591889313719(lat), 156.626748769570(lng)
Province: Western
Ward: Ndovele
Village: Zutapati
Cycle: Cycle5
Nature of Sub-project: New

-
-
-

Subproject Objective: To provide accessibility to fresh water supply system usable for drinking and washing for Zutapati community.

Brief Description: Zutapati village has long been not having proper water supply system easily accessible for drinking, washing, bathing and cooking. The community had to walk a distance to fetch water. Out of desperation, they once attempted to create their own piped water by using old water supply pipes from Legoe primary school to draw water from an inland source to a location of around 10-15 minutes walking distance from the village. Currently the proposed water supply SP would be the first of its kind for the community and is highly anticipated to yield maximum benefit, thus draw wide community support.

Date approved by Province: 09/06/2017
Date TDF approved: 30/11/2016
Community Helper name: Ronnette Paul - Maelagi

Is this project added because of a discontinued project: No

Subproject Type: Water Supply (Gravity Fed)
Sector: Health
Subsector: Water Supply

Date of SIC establishment meeting: 29/11/2015
Agreed name of SIC: Zutapati Water Supply SIC

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson Kilden Johnmark Male
Treasurer/Accountant Dently Vavozo Male
Secretary Stella Haron Female
Technical Officer Richard Mula Male
Youth Member Maclean Mathew Male
Member1 Lamah Salau Male
Member2 Hilen Hilton Female
Member3 Doreen Salau Female

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 112 102 214
15 - 24 yrs 115 107 222
25 - 59 yrs 229 238 467
60+ yrs 44 43 87
Total 500 490 990
People with special needs: 16 Households: 150


Names of villages expected to benefit and number of beneficiaries:

Zutapati

Age Group Male Female Total
0 - 14 yrs 27 24 51
15 - 24 yrs 12 9 21
25 - 59 yrs 40 40 80
60+ 8 9 17
Total 87 82 169
People with special needs 6 Households 30

Liangai

Age Group Male Female Total
0 - 14 yrs 0 0 0
15 - 24 yrs 43 42 85
25 - 59 yrs 129 142 271
60+ 0 0 0
Total 172 184 356
People with special needs 3 Households 41

New Boro

Age Group Male Female Total
0 - 14 yrs 85 78 163
15 - 24 yrs 60 56 116
25 - 59 yrs 60 56 116
60+ 36 34 70
Total 241 224 465
People with special needs 7 Households 79

Work plan stages and activities:

Stage1 Completed
Pre-construction workshop, identify construction supervisor, collect sand & gravel, milling of timber and brushing pipeline routes. Yes
Procurement of Hardware materials including fuel pump & spares and shipment to SP site. Yes
Transport of materials to village. Yes
Stage2 Completed
Construct intake structure, excavate pipe trench to first tank, install 50mm PE pipeline from intake. Yes
Construct 3000g Feroo-cement tank, construct pump shed, excavate pipeline trench to 2000g tank, install pipeline to 2000g tank, construct 2000g Ferro-cement tank. Yes
Excavate pipe trench to standpipes, construct standpipes, install pipeline from tank to standpipes, test system for leaks and bury pipelines. No
Stage3 Completed
Construct concrete base for tank, install 1000g aluminium tank. Yes
Excavate pipe trenches, construct standpipes, install pipelines to standpipes, test system for leaks and bury pipeline. No
Operation and maintenance training, hygiene promotion and sanitation promotion. No

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $
1 Mobilization Unknown Services 7750
2 Procurement of hardware materials Unknown Goods 145275
3 Cutting & threading of galvanized pipes Unknown Work 2100
4 Purchase of fuel pump & spares Unknown Goods 6500
5 Milling of timber Unknown Work 1375
6 Transport of hardware materials Unknown Services 15000
7 Transport of sand and gravel Unknown Work 2000
8 Supervision of water supply construction Unknown Work 20000

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan:

Operation and Maintenance Monitoring Report: