Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

The objective of this programme is to improve access to basic services in rural areas
and the production and productivity of farmers.

Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

Dunde Water Supply

Print

latest report image

Status: Completed
100%
0%

100% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Dunde Water Supply
GPS Coordinates: -8.328761000000(lat), 157.275172000000(lng)
Province: Western
Ward: Nusa roviana
Village: Dunde
Cycle: Cycle5
Nature of Sub-project: New

-
-
-

Subproject Objective: To provide clean safe, secure and reliable water supply for Dunde Community.

Brief Description: Water scarcity has been a longstanding problem in Munda area including Dunde village. The community has hand dug well faciliteis and private water tanks as their only water resource at present. The proposed development of improved wells with hand pumps and pumped bore holes under RDPII support will greatly serve the community by providing water for bath, laundry , washing etc. This would also cut travelling to distances by the community to fetch water.

Date approved by Province: 09/06/2017
Date TDF approved: 30/11/2016
Community Helper name: John Havea

Is this project added because of a discontinued project: No

Subproject Type: Water Supply (Borehole Hand pump)
Sector: Health
Subsector: Water Supply

Date of SIC establishment meeting: 21/11/2015
Agreed name of SIC: DUNDE WATSAN COMMITTEE

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson Rev. Tioko Beti Male
Treasurer/Accountant Saisuli Hitu Female
Secretary Mccoy Benette Male
Technical Officer Ronold Daka Male
Youth Member Kubata Lemati Male
Member1 Sender Siosi Female
Member2 Mark Kerry Male
Member3 Lasu Wicham Male

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 289 181 470
15 - 24 yrs 137 130 267
25 - 59 yrs 394 365 759
60+ yrs 31 38 69
Total 851 714 1565
People with special needs: 6 Households: 301


Names of villages expected to benefit and number of beneficiaries:

Dunde

Age Group Male Female Total
0 - 14 yrs 232 125 357
15 - 24 yrs 103 95 198
25 - 59 yrs 294 270 564
60+ 21 30 51
Total 650 520 1170
People with special needs 4 Households 224

Kekehe

Age Group Male Female Total
0 - 14 yrs 57 56 113
15 - 24 yrs 34 35 69
25 - 59 yrs 100 95 195
60+ 10 8 18
Total 201 194 395
People with special needs 2 Households 77

Work plan stages and activities:

Stage1 Completed
Pre-construction workshop, confirm sites for boreholes, confirm sites for wells/hand pumps Yes
Identify construction supervisor Yes
Collect sand & gravel, milling of timber Yes
Purchase hardware materials, purchase hand pumps, purchase concrete blocks & transport materials to site Yes
Stage2 Completed
Construction boreholes (6): construction of boreholes, development of boreholes Yes
construct wells with suspended slabs(10): caste suspended slabs , caste cover slabs, concrete around base of existing headwalls, install cover slabs, Yes
Construct concrete aprons drainage channels Yes
Install hand pumps Yes
Stage3 Completed
Construct buried tubewells (20): Install PVC casing/screens, backfill bottom of wells with compacted gravel, caste concrete seals on top of gravel Yes
Backfill wells with compacted ground, construct concrete aprons drainage channels Yes
Install hand pumps Yes

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $
1 Mobilisation unknown Services 5800
2 Procurement/ supply of hardware materials unknown Goods 180965
3 Supply & installation of sol Mark 5 hand pump unknown Services 102895
4 Timber Milling unknown Goods 2840
5 Freight of hardware materials from Honiara unknown Services 15000
6 Transport of hardware materials locally unknown Services 7500
7 Construction supervisor unknown Services 30000

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan:

Operation and Maintenance Monitoring Report: