latest report image

Status: Ongoing
70%
0%

70% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Dukwasi Community Hall
GPS Coordinates: -8.755186064802(lat), 160.70647940935(lng)
Province: Malaita
Ward: Auki
Village: Dukwasi
Cycle: Cycle5
Nature of Sub-project: New

-
-
-

Subproject Objective: Used purposely for meetings, gatherings or feasting during church activities and small indoor games (sport).

Brief Description: A standard type of building with concrete slabbing and columns plus roofing with open space to cater for sports activities and community meeting.

Date approved by Province: 15/06/2016
Date TDF approved: 20/05/2016
Community Helper name: Terry Oiaka

Is this project added because of a discontinued project: No

Subproject Type: Community Hall
Sector: Housing and Community
Subsector: Community Development

Date of SIC establishment meeting: 29/11/2015
Agreed name of SIC: Dukwasi

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson Nelson Lui Ata Male
Treasurer/Accountant Walter Misitana Male
Secretary Lilian Gwali Female
Technical Officer John Wula Male
Youth Member Jerry Tomalau Male
Member1 Uriel Gwali Male
Member2 Peter Kela Male
Member3 Clera Haemanu Female

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 115 123 238
15 - 24 yrs 68 62 130
25 - 59 yrs 138 125 263
60+ yrs 10 14 24
Total 331 324 655
People with special needs: 8 Households: 131


Names of villages expected to benefit and number of beneficiaries:

Dukwasi

Age Group Male Female Total
0 - 14 yrs 115 123 238
15 - 24 yrs 68 62 130
25 - 59 yrs 138 125 263
60+ 10 14 24
Total 331 324 655
People with special needs 8 Households 131

Work plan stages and activities:

Stage1 Completed
Community mobilization - Designing, labor & materials Yes
Stage2 Completed
Log preparation - Milling timber Yes
Stage3 Completed
Construction of foundation, trenches, excavation of footings Yes
Stage4 Completed
Construction of beams, casing, pouring, fabrication of trusses Yes
Stage5 Completed
Construction of roofing and purling, setting Yes
iron roofing covering Yes
Stage6 Completed
Final touches No
Cleaning up No
Sub project completed No
100% of RDP funds acquitted by SIC and sent to PCU for audit Yes

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $
1 Hardware materials Unknown Goods 86620
2 Contractors Unknown Work 43300
3 Milling Cost & timber Unknown Goods 64080

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan:

Operation and Maintenance Monitoring Report: