Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

The objective of this programme is to improve access to basic services in rural areas
and the production and productivity of farmers.

Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

Arakao Community Hall

Print

latest report image

Status: Ongoing
75%
0%

75% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Arakao Community Hall
GPS Coordinates: -9.28497(lat), 161.241492(lng)
Province: Malaita
Ward: Areare
Village: Arakao
Cycle: Cycle5
Nature of Sub-project: New

-
-
-

Subproject Objective: To help community facilitate its program on a proper venue that caters for up to 100 participants/catchment.

Brief Description: A building with concrete structure, column post with roofing structure made of timber up to 100 people usage.

Date approved by Province: 09/06/2017
Date TDF approved: 20/05/2016
Community Helper name: Joshua Kikimae

Is this project added because of a discontinued project: No

Subproject Type: Community Hall
Sector: Housing and Community
Subsector: Community Development

Date of SIC establishment meeting: 04/12/2015
Agreed name of SIC: Arakao SIC

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson John Waraa'ia Male
Treasurer/Accountant Thomas Aruhane Male
Secretary Alick Kauwawa Male
Technical Officer Michael Aiwaia Male
Youth Member Mathew Waikira Male
Member1 Maddy Ipala Female
Member2 John Uipaeloa Male
Member3

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 65 56 121
15 - 24 yrs 105 70 175
25 - 59 yrs 140 115 255
60+ yrs 26 23 49
Total 336 264 600
People with special needs: 3 Households: 93


Names of villages expected to benefit and number of beneficiaries:

Arakao

Age Group Male Female Total
0 - 14 yrs 25 24 49
15 - 24 yrs 25 20 45
25 - 59 yrs 40 35 75
60+ 6 5 11
Total 96 84 180
People with special needs 1 Households 25

Masupa

Age Group Male Female Total
0 - 14 yrs 40 32 72
15 - 24 yrs 80 50 130
25 - 59 yrs 100 80 180
60+ 20 18 38
Total 240 180 420
People with special needs 2 Households 68

Work plan stages and activities:

Stage1 Completed
Mobilization – site clearing, collection of sand and gravel Yes
Timber milling, handling and transportation Yes
Procurement of Materials & Transportation Yes
Stage2 Completed
Foundation construction Yes
Roof construction Yes
Interior completion, Louver frames and painting No
Stage3 Completed
Final Finishing and Handing Over No
100% of RDP funds acquitted by SIC and sent to PCU for audit Yes

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $
1 Timber Milling Contractor Unknown Work 10000
2 Building contractor Uknown Work 25000
3 Plumbing contractor Uknown Work 3000

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan:

Operation and Maintenance Monitoring Report: