Subproject Objective:
To provide safe, healthy drinking water supply for Komukama community.
Brief Description:
To construct and build proper and safe water supplu for the community. The Komukama community and nearby communities are prepared to contribute unskilled labour and local materials such as, gravel ,sand, trees for timber and other things required by the program. RDP to provide funding to meet imported materials and technical skills to complete the subproject.
Date approved by Province:
21/09/2016
Date TDF approved:
13/05/2016
Community Helper name:
Noelyn Palua
Is this project added because of a discontinued project:
No
Subproject Type:
Water Supply (Rain Catchment System) & Hand Dug Well
Sector:
Health
Subsector:
Water Supply
Date of SIC establishment meeting:
10/08/2016
Agreed name of SIC:
Komukama Community Rural Development Project
SIC Executive Members:
Position (given)
Name
Gender M/F (select)
Chairperson
Robert Tumu
Male
Treasurer/Accountant
Paul Thungea
Male
Secretary
John Tule
Male
Technical Officer
Edmon Saelea
Male
Youth Member
Member1
Nathaniel Nongia
Male
Member2
Nester Ghaokale
Female
Member3
Lydia Matekali
Female
Total Beneficiaries
Age Group
Male
Female
Total
0 - 14 yrs
92
52
144
15 - 24 yrs
38
36
74
25 - 59 yrs
49
63
112
60+ yrs
13
13
26
Total
192
164
356
People with special needs:
5
Households:
79
Names of villages expected to benefit and number of beneficiaries:
Komukama
Age Group
Male
Female
Total
0 - 14 yrs
92
52
144
15 - 24 yrs
38
36
74
25 - 59 yrs
49
63
112
60+
13
13
26
Total
192
164
356
People with special needs
5
Households
79
Work plan stages and activities:
Stage1
Completed
Pre-construction workshop, Confirm sites for rain catchment & well
Yes
Identify construction supervisor, milling of timber
Yes
Collect sand, gravel, stones, purchase materials
Yes
Prepare hand pump assembly, transport of materials to site
Yes
Dig post holes
Yes
Stage2
Completed
Construct rain catchments, tank stands
Yes
Install tanks, gutters & down pipes
Yes
Construct concrete tank platform
Yes
Construct tap stand
Yes
Place tanks on tank platform
Yes
Stage3
Completed
Install gutters & down pipes, Dig pipe trench to tap stand
Yes
Connect pipes from tanks to tank stand
Yes
Additional water tanks in replacement of hand dug wells
Yes
Stage4
Completed
Completion
Yes
Community procurement plan. List of up to 20 items/contracts:
#
Contract Title
Contractor
Select Goods/Work/Services
Cost SBD $
1
Mobilization
Unknown
Work
2500
2
Supply of Hardware Materials
Unknown
Goods
94738
3
Supply of 3000 Liter Poly Tanks
Unknown
Goods
69600
4
Supply of 1000 Gallon Aluminium Tanks
Unknown
Goods
31500
5
Supply of Sol Mark 5 Hand Pump
Unknown
Goods
6762
6
Milling of timber
Unknown
Services
20100
7
Construction of rain catchment systems
Unknown
Services
8000
8
Construction of rain catchment system at Anglican Church