Tamboko Water Supply / Monitoring Report / 01/05/2018 03:00

<% completition_percent %>% Completion


Date of monitoring visit: 01/05/2018
Fred. Gale

Work plan stages and activities:

<% work_stage.stage %> Completed
<% work_activity.description %> Yes Yes No

Implementation Problem or Procurement issues:

Issue Date Created Date Updated Resolved Y/N
Drilling can not proceed because PVC high pressure pipes is out of stock in honiara. this pvc pipe must be available on site before drilling commence 25/11/2016 14/12/2016 Yes
Engineers need to reassess the pending issue after doing water quality test. 26/10/2017 26/10/2017 Yes
Poor community participation. PSU met supervisor to complete the remaining work. Organise with him to complete activities before second week of May 2018. 01/05/2018 01/05/2018 Yes
Pump is the problem 22/06/2018 22/06/2018 Yes
Water pump is a problem, need a pump that within the specification. 27/07/2018 27/07/2018 Yes
Pending certification by engineers. 03/09/2018 03/09/2018 Yes

Are Financial records being kept up to date: Yes

Have records of community contributions been updated: Yes

Are there any changes to other contributions? No

Other Comment: Only main pipe from storage tank to the borehole is not connected. This work to complete the job is scheduled for 2 weeks only.