Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

The objective of this programme is to improve access to basic services in rural areas
and the production and productivity of farmers.

Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

Gwailiki Community Hall

Print

latest report image

Status: Ongoing
58.3%
0%

58.3% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Gwailiki Community Hall
GPS Coordinates: -8.718060787970(lat), 160.703618091864(lng)
Province: Malaita
Ward: Buma
Village: Gwailiki
Cycle: Cycle5
Nature of Sub-project: New

-
-
-

Subproject Objective: Purposely to accommodate community meetings, church programs, etc.

Brief Description: Is a raised floor slabbing concrete with column and roofing, walling, beams with timber. A center for all the Anglican Communities with an aim to host big gatherings.

Date approved by Province: 15/06/2016
Date TDF approved: 20/05/2016
Community Helper name: Terry Oiaka

Is this project added because of a discontinued project: No

Subproject Type: Community Hall
Sector: Housing and Community
Subsector: Community Development

Date of SIC establishment meeting: 02/12/2015
Agreed name of SIC: Gwailiki Infrastructure Committee

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson Samuel Maelisu'u Male
Treasurer/Accountant Cicel Kalo Male
Secretary Simon Nofa Male
Technical Officer Chris Laekalia Male
Youth Member Rosemary Maetofea Female
Member1 Alice Kalo Female
Member2 George Ming Male
Member3 Rosina Maelalo Female

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 146 134 280
15 - 24 yrs 82 64 146
25 - 59 yrs 101 98 199
60+ yrs 18 7 25
Total 347 303 650
People with special needs: 2 Households: 107


Names of villages expected to benefit and number of beneficiaries:

Gwailiki

Age Group Male Female Total
0 - 14 yrs 35 30 65
15 - 24 yrs 14 8 22
25 - 59 yrs 30 24 54
60+ 4 2 6
Total 83 64 147
People with special needs 0 Households 22

Faidaedae

Age Group Male Female Total
0 - 14 yrs 19 22 41
15 - 24 yrs 19 6 25
25 - 59 yrs 11 12 23
60+ 3 3 6
Total 52 43 95
People with special needs 1 Households 16

Dadaesalu

Age Group Male Female Total
0 - 14 yrs 24 22 46
15 - 24 yrs 13 15 28
25 - 59 yrs 25 24 49
60+ 3 1 4
Total 65 62 127
People with special needs 0 Households 19

Gwaibale

Age Group Male Female Total
0 - 14 yrs 43 50 93
15 - 24 yrs 17 21 38
25 - 59 yrs 19 22 41
60+ 6 1 7
Total 85 94 179
People with special needs 1 Households 32

Tatafurade

Age Group Male Female Total
0 - 14 yrs 25 10 35
15 - 24 yrs 19 14 33
25 - 59 yrs 16 16 32
60+ 2 0 2
Total 62 40 102
People with special needs 0 Households 18

Work plan stages and activities:

Stage1 Completed
Community Mobilization - Site clearance, gravel & sand Yes
Timber milling and carrying on site Yes
Procurement of hardware materials Yes
Stage2 Completed
Construction of floor slabbing Yes
Construction of columns Yes
Construction of roofing Yes
Construction of external walls & frames Yes
Stage3 Completed
Plumbing works No
Finishing job No
100% of RDP funds acquitted by SIC and sent to PCU for audit No
Cleaning up No
Sub Project completed No

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $
1 Hardware materials Unknown Goods 161731
2 Contractor Unknown Work 25100
3 Design Unknown Services 2000

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan:

Operation and Maintenance Monitoring Report: