Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

The objective of this programme is to improve access to basic services in rural areas
and the production and productivity of farmers.

Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

Anofiu School Classroom

Print

latest report image

Status: Completed
100%
0%

100% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Anofiu School Classroom
GPS Coordinates: -8.772402000000(lat), 160.907198000000(lng)
Province: Malaita
Ward: Nafinua
Village: Anofiu
Cycle: Cycle5
Nature of Sub-project: Expansion / Extension

-
-
-

Subproject Objective: To complete a permanent classroom built by the community and enable students to move to a more spacious and comfortable rooms that caters for more intake of children.

Brief Description: Anofiu community school is experiencing a high influx of children attending their school. Initial drive to solve the problem enables them to build a two story building through community contribution. They were unable to complete the building and therefore identified as their priority for RDP community support project.

Date approved by Province: 09/06/2017
Date TDF approved: 20/05/2016
Community Helper name: Augustine Waki

Is this project added because of a discontinued project: No

Subproject Type: Classroom
Sector: Education
Subsector: Education not defined by level ( inc vocational)

Date of SIC establishment meeting: 16/01/2016
Agreed name of SIC: Anofiu SIC

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson Marthius Billy Male
Treasurer/Accountant Daniel Kirifooa Male
Secretary Samson Ata Male
Technical Officer Peter Maenene Male
Youth Member Angella Bau Female
Member1 Auther Ferakwakwa Male
Member2 David Ina Male
Member3 George Irobina Male

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 104 127 231
15 - 24 yrs 121 133 254
25 - 59 yrs 64 67 131
60+ yrs 3 2 5
Total 292 329 621
People with special needs: 3 Households: 62


Names of villages expected to benefit and number of beneficiaries:

Anofiu

Age Group Male Female Total
0 - 14 yrs 104 127 231
15 - 24 yrs 121 133 254
25 - 59 yrs 64 67 131
60+ 3 2 5
Total 292 329 621
People with special needs 3 Households 62

Work plan stages and activities:

Stage1 Completed
Community Mobilization Yes
Sand & Gravel collection to site Yes
Timber milling, timber handling Yes
Stage2 Completed
Procurement of hardware materials Yes
Stage3 Completed
Flooring & Walling Yes
Stage4 Completed
Concrete slab & Brick walling Yes
Stage5 Completed
Windows, doors and painting Yes
Stage6 Completed
Final finishing Yes
Cleaning up Yes
Sub project complete Yes

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $
1 Milling contractor Unknown Work 18000
2 Building Contractor Unknown Work 13000
3 Plumbing Contractor Unknown Work 3000
4 Hardware Supplier Unknown Goods 137316

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan:

Operation and Maintenance Monitoring Report: