Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

The objective of this programme is to improve access to basic services in rural areas
and the production and productivity of farmers.

Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

Kaonasugu Community Hall

Print

latest report image

Status: Ongoing
93.3%
0%

93.3% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Kaonasugu Community Hall
GPS Coordinates: -10.414590043698(lat), 161.7816370769(lng)
Province: Makira/Ulawa
Ward: Bauro west
Village: Kaonasugu
Cycle: Cycle5
Nature of Sub-project: New

-
-
-

Subproject Objective: To provide accommodation to visitors & proper meeting venue for Kaonasugu and surrounding communities.

Brief Description: The project will address the community's long term difficulty in accommodation visitors to community, provide proper meeting venue, conference facility, fundraising and proper recreation area for Kaonasugu and surrounding communities and the general public during big occasions.

Date approved by Province: 04/12/2015
Date TDF approved: 25/08/2016
Community Helper name: Walter Wate

Is this project added because of a discontinued project: No

Subproject Type: Community Hall
Sector: Housing and Community
Subsector: Community Development

Date of SIC establishment meeting: 09/12/2015
Agreed name of SIC: Kaonasugu Community Hall

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson Ben Mahana Male
Treasurer/Accountant McPherson Haga Male
Secretary Macdonald Haga Male
Technical Officer Thomas Watarua Male
Youth Member Loloy Moni Male
Member1 Joana. M Female
Member2 Everlyn Danoma Female
Member3 Sydney Haga Male

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 160 133 293
15 - 24 yrs 108 97 205
25 - 59 yrs 151 145 296
60+ yrs 23 17 40
Total 442 392 834
People with special needs: 20 Households: 195


Names of villages expected to benefit and number of beneficiaries:

Kaonasugu

Age Group Male Female Total
0 - 14 yrs 50 45 95
15 - 24 yrs 45 40 85
25 - 59 yrs 30 35 65
60+ 4 5 9
Total 129 125 254
People with special needs 1 Households 78

Kokana

Age Group Male Female Total
0 - 14 yrs 36 29 65
15 - 24 yrs 23 25 48
25 - 59 yrs 45 36 81
60+ 11 7 18
Total 115 97 212
People with special needs 6 Households 38

Ago

Age Group Male Female Total
0 - 14 yrs 18 14 32
15 - 24 yrs 12 8 20
25 - 59 yrs 24 21 45
60+ 3 2 5
Total 57 45 102
People with special needs 3 Households 24

Waioto

Age Group Male Female Total
0 - 14 yrs 39 30 69
15 - 24 yrs 12 8 20
25 - 59 yrs 34 33 67
60+ 1 0 1
Total 86 71 157
People with special needs 4 Households 32

Tawapuna

Age Group Male Female Total
0 - 14 yrs 17 15 32
15 - 24 yrs 16 16 32
25 - 59 yrs 18 20 38
60+ 4 3 7
Total 55 54 109
People with special needs 6 Households 23

Work plan stages and activities:

Stage1 Completed
Procurement of hardware materials Yes
Site development & construction of storage shed Yes
Collection of sand, gravel & stone Yes
Stage2 Completed
Timber milling and seasoning Yes
Set up of layout Yes
Stage3 Completed
Construction of piles, posts soak away septic tank Yes
Construction of foundation Yes
Construction of wall structure/fixing of bearers, floor joists, bottom plates, roof beams, veranda beams, etc. Yes
Construction of roof, fixing up of rafters, purlins ridge board, roof bracing gutters. Yes
Stage4 Completed
Roof cladding & fixing up of ridges Yes
Construction and fixing up of doors, windows, Yes
Wall cladding, flooring and ceiling Yes
Fixing of toilet pans, water pipes & basins No
Stage5 Completed
Painting and finishing touches Yes
Cleaning up & Sub project fully complete Yes

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $
1 Timber Milling Unknown Goods 9400
2 Hardware materials Unknown Goods 157600
3 Contractor/Supervisor Unknown Goods 23000
4 Freight/Fares Unknown Services 10000

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan:

Operation and Maintenance Monitoring Report: