Subproject Objective:
The classroom building will provide an improved school infrastructure for a conducive learning environment for our school aged children. The catchment area for the Mona Primary School is quite large so such a building will relieve the acute space the school has.
Brief Description:
The Mona Primary School Classroom building will be a standard three (3) classroom block building measuring 22.5m length x 6m width raised on concrete columns. It will be a timber framed building cladded with roofing iron sheets. The building will be built according to the design specifications.
Date approved by Province:
15/03/2017
Date TDF approved:
25/04/2016
Community Helper name:
Alistair Lemoba
Is this project added because of a discontinued project:
No
Subproject Type:
Classroom
Sector:
Education
Subsector:
Primary Education
Date of SIC establishment meeting:
22/11/2015
Agreed name of SIC:
Mona Primary School Building
SIC Executive Members:
Position (given)
Name
Gender M/F (select)
Chairperson
Darton Mekai
Male
Treasurer/Accountant
Elina Mekupe
Female
Secretary
Priscilla. L
Female
Technical Officer
Japhet Menaplo
Male
Youth Member
Clera Melinda
Female
Member1
Moses Mekupe
Male
Member2
Ben Metopa
Male
Member3
Ruth Tungale
Female
Total Beneficiaries
Age Group
Male
Female
Total
0 - 14 yrs
151
134
285
15 - 24 yrs
79
56
135
25 - 59 yrs
207
214
421
60+ yrs
12
13
25
Total
449
417
866
People with special needs:
10
Households:
156
Names of villages expected to benefit and number of beneficiaries:
Napir
Age Group
Male
Female
Total
0 - 14 yrs
20
18
38
15 - 24 yrs
5
7
12
25 - 59 yrs
31
42
73
60+
0
0
0
Total
56
67
123
People with special needs
1
Households
28
Nepa
Age Group
Male
Female
Total
0 - 14 yrs
28
15
43
15 - 24 yrs
27
8
35
25 - 59 yrs
31
39
70
60+
2
4
6
Total
88
66
154
People with special needs
0
Households
23
Pala
Age Group
Male
Female
Total
0 - 14 yrs
31
22
53
15 - 24 yrs
13
14
27
25 - 59 yrs
25
23
48
60+
2
2
4
Total
71
61
132
People with special needs
1
Households
26
Yc
Age Group
Male
Female
Total
0 - 14 yrs
11
9
20
15 - 24 yrs
11
6
17
25 - 59 yrs
38
30
68
60+
0
0
0
Total
60
45
105
People with special needs
1
Households
22
Lvepx
Age Group
Male
Female
Total
0 - 14 yrs
49
51
100
15 - 24 yrs
14
12
26
25 - 59 yrs
62
61
123
60+
5
3
8
Total
130
127
257
People with special needs
1
Households
35
Balo
Age Group
Male
Female
Total
0 - 14 yrs
12
19
31
15 - 24 yrs
9
9
18
25 - 59 yrs
20
19
39
60+
3
4
7
Total
44
51
95
People with special needs
6
Households
22
Work plan stages and activities:
Stage1
Completed
Procurement of hardware materials
Yes
Site development and construction of storage shed
Yes
Collection of sand, gravel and stones
Yes
Stage2
Completed
Timber milling and seasoning
Yes
Set up layout
Yes
Construction of foundation piles/posts,
Yes
Construction Bearers and Floor joist
Yes
Construction of roof (fixing up of rafters, purling, ridge board, roof bracing, gutters)
Yes
Stage3
Completed
Roof cladding and fixing up of ridges;
Yes
Wall cladding, flooring, ceiling;
Yes
Construction and fixing up of doors, windows, toilet pan, water pipes, basins, etc
Yes
Painting and finishing touches;soak away, septic tank, etc
Yes
All environmental works completed;
Yes
Stage4
Completed
Cleaning up
Yes
Sub project completed
Yes
100% of RDP funds acquitted by SIC and sent to PCU for audit
Yes
Community procurement plan. List of up to 20 items/contracts: