Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

The objective of this programme is to improve access to basic services in rural areas
and the production and productivity of farmers.

Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

Baimawa Water Supply

Print

latest report image

Status: Completed
100%
0%

100% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Baimawa Water Supply
GPS Coordinates: -10.827810674518(lat), 165.87580448624(lng)
Province: Temotu
Ward: Nanggu/lord howe
Village: Baimawa
Cycle: Cycle5
Nature of Sub-project: New

-
-
-

Subproject Objective: The community to have access to clean water for drinking and washing which will be readily available and one that would take little of a time to get it.

Brief Description: The Baimawa Water Supply project is a water supply system designed to be a solar powered water pumps. Firstly the water is supplied by gravitational feed from a spring source into a 2000 gallons ferrocement storage tank. The 2000 gallons ferrocement storage tank will be installed with a solar powered water pump to supply water to two 1000 gallons aluminium water tanks elevated on galvanized iron posts which will then supply water to outlet stand pipes at the designated locations around the community.

Date approved by Province: 15/03/2016
Date TDF approved: 12/03/2018
Community Helper name: Alistair Lemoba

Is this project added because of a discontinued project: No

Subproject Type: Water Supply (Gravity Fed)
Sector: Health
Subsector: Water Supply

Date of SIC establishment meeting: 23/11/2015
Agreed name of SIC: Baimawa Water Supply SIC

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson Abraham Mepoulo Male
Treasurer/Accountant Lydia Ilatha Female
Secretary Lillian Menapa Female
Technical Officer George Dolau Male
Youth Member Joana. M Female
Member1 Rachel Moi Female
Member2 Batholomew Takiato Male
Member3 John Still Male

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 40 33 73
15 - 24 yrs 24 16 40
25 - 59 yrs 41 52 93
60+ yrs 3 6 9
Total 108 107 215
People with special needs: 0 Households: 44


Names of villages expected to benefit and number of beneficiaries:

Baimawa

Age Group Male Female Total
0 - 14 yrs 40 33 73
15 - 24 yrs 24 16 40
25 - 59 yrs 41 52 93
60+ 3 6 9
Total 108 107 215
People with special needs 0 Households 44

Work plan stages and activities:

Stage1 Completed
Procurement of hardware materials including water tanks, solar pumps Yes
Site preparation location of storage tank, mark and brush pipeline Yes
Collection of sand and gravel Yes
Stage2 Completed
Timber milling and seasoning Yes
Construction of foundation for the dam Yes
Stage3 Completed
Construction of ferro and elevated tanks, plastering and paintings of rails Yes
Construction of solar panels & stand pipes Yes
Stage4 Completed
Excavate pipeline Yes
Connect stand pipes Yes
Test system for leakages, bury pipe line Yes
All environmental works completed Yes
Completion Yes

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $
1 Hardware Materials Unknown Goods 219890
2 Plumbing Work Unknown Work 20000

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan:

Operation and Maintenance Monitoring Report: