Solomon Islands Ministry of Development, Planning and Aid Coordination
<% completition_percent %>% Completion
<% work_stage.stage %> | Completed |
---|---|
<% work_activity.description %> |
|
Issue | Date Created | Date Updated | Resolved Y/N |
---|---|---|---|
there are atleast target of 9 cyclone houses to be constructed and todate minimal progress has been experience due to weak or lack of support from community as reported and differences among SIC members. | 21/06/2017 | 30/06/2017 | No |
Movement of some key members (to Honiara) for other personal businesses possibly contributed to any process of settling their issues and its seems continue to cause huge gap in the implementation of the SP. With the remain 3 SIC members and probably repla | 21/06/2017 | 02/01/2018 | Yes |