Solomon Islands Ministry of Development, Planning and Aid Coordination
<% completition_percent %>% Completion
<% work_stage.stage %> | Completed |
---|---|
<% work_activity.description %> |
|
Issue | Date Created | Date Updated | Resolved Y/N |
---|---|---|---|
Differences & Movement among SIC members | 26/06/2017 | 02/01/2018 | Yes |
Labor with non-financial resources remain the core factor causing slow or no progress | 18/12/2017 | 03/06/2019 | Yes |
Materials (timbers) devalue in its quality state a great concern. Other hardware stuff likely got lost or missing slowly. | 18/12/2017 | 17/07/2018 | Yes |
Shortfall of hardware materials - MP and WDC/MPA were approached by SIC and promising pledges to support is in place and should have the required materials onsite by July 2018. | 01/06/2018 | 03/06/2019 | Yes |