Vovohe Water Supply

Print

latest report image

Status: Ongoing
0%
41.7%

41.7% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Vovohe Water Supply
GPS Coordinates: -8.115733(lat), 157.091753(lng)
Province: Western
Ward: South kolombangara
Village: Vovohe 1
Cycle: Cycle6
Nature of Sub-project: New

-
-
-

Subproject Objective: To provide accessibility to quality and reliable water services for Vovohe village.

Brief Description: Vovohe Community is a marginalized community that do not have access to basic services such as schools, clinics, water supply and other basic services. Students and sick patients were travelling by local dugout canoes for 20 minutes and by truck to KFPL Ringi station to access such services. However for the decade the community were also travelling by local dugout canoes along the nearby rivers to access drinking water and other domestic uses. This project will be a water tank with a stand alone catchment and an existing houses. The project will provide safe drinking water and domestic uses to the community. This project will be a great help to Vovohe Community.

Date approved by Province: 19/03/2019
Date TDF approved: 23/10/2019
Community Helper name: Ronnette Paul - Maelagi

Is this project added because of a discontinued project: No

Subproject Type: Water Supply (Rain Catchment System)
Sector: Health
Subsector: Water Supply

Date of SIC establishment meeting: 11/12/2019
Agreed name of SIC: Vovohe Water Tank

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson Tom Sotere Male
Treasurer/Accountant Bolas Mada Male
Secretary Willie Henry Male
Technical Officer Mula Mathew Male
Youth Member Magaret Jeffery Female
Member1 Tony Gua Male
Member2 Idigula Eddie Female
Member3 Grace Enoch Female

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 24 22 46
15 - 24 yrs 12 6 18
25 - 59 yrs 37 32 69
60+ yrs 3 1 4
Total 76 61 137
People with special needs: 1 Households: 25


Names of villages expected to benefit and number of beneficiaries:

Vovohe 1

Age Group Male Female Total
0 - 14 yrs 24 22 46
15 - 24 yrs 12 6 18
25 - 59 yrs 37 32 69
60+ 3 1 4
Total 76 61 137
People with special needs 1 Households 25

Work plan stages and activities:

Stage1 Completed
Confirm sites for rain catchments Yes
Timber milling & construction supervisors contact Yes
Site preparation of Rain Water Catchment Yes
Stage2 Completed
Collect sand & gravel No
Milling of timbers No
Procurement of hardware materials Yes
Transporting of hardware materials Yes
Stage3 Completed
Dig post holes No
Construct rain catchments No
Construct tanks stands No
Install tanks, gutter & downpipe No
Stage4 Completed
Site clean up and testing No

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $
1 Timber milling Unknown Services 11612
2 Transport & Logistics Unknown Services 2500
3 Administration Unknown Goods 2223
4 Hardware Materials & Tools Unknown Goods 141277
5 Freights Unknown Services 22000
6 Labor Unknown Services 15000
7 Tools Unknown Goods 5388

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan:

Operation and Maintenance Monitoring Report: