RDP Community MP MPA Provincial Government CRISP RWASH Other
Name:
Goveo Community Hall
GPS Coordinates:
-7.95332(lat), 159.199411(lng)
Province:
Isabel
Ward:
Kokota
Village:
Goveo
Cycle:
Cycle6
Nature of Sub-project:
New
-
-
-
Subproject Objective:
To build a permanent community hall which will provide conducive venue and other convenience facilities to cater for training, information distribution center and accommodations.
Brief Description:
An improved and proper community hall building is the most priority need for the improvement of services in our community and nearby areas. The current state of our community meeting hall is deteriorating, poor and not conducive for any community or ward meetings, information dissemination activities including storage. This community hall will consist of one large conference room, one meeting room, four bedrooms, and four toilet rooms to meet the desired needs. Community and Isabel provincial government has pledge its support to contribute in-kind in the construction of this RDP supported community hall project.
Date approved by Province:
23/10/2019
Date TDF approved:
27/01/2019
Community Helper name:
Selwyn Getu
Is this project added because of a discontinued project:
No
Subproject Type:
Community Hall
Sector:
Housing and Community
Subsector:
Community Development
Date of SIC establishment meeting:
10/03/2018
Agreed name of SIC:
Goveo Community Hall
SIC Executive Members:
Position (given)
Name
Gender M/F (select)
Chairperson
Raymond Kakau
Male
Treasurer/Accountant
Anthony Basako
Male
Secretary
Bravery Masi Tete
Male
Technical Officer
Hanget Legu
Male
Youth Member
Mark Havilegu
Male
Member1
Deborah
Female
Member2
Alina Tena
Female
Member3
Serah Lui
Female
Total Beneficiaries
Age Group
Male
Female
Total
0 - 14 yrs
91
99
190
15 - 24 yrs
45
41
86
25 - 59 yrs
103
80
183
60+ yrs
5
6
11
Total
244
226
470
People with special needs:
4
Households:
119
Names of villages expected to benefit and number of beneficiaries:
Goveo
Age Group
Male
Female
Total
0 - 14 yrs
91
99
190
15 - 24 yrs
45
41
86
25 - 59 yrs
103
80
183
60+
5
6
11
Total
244
226
470
People with special needs
4
Households
119
Work plan stages and activities:
Stage1
Completed
Procurement/Preliminaries
Yes
Procurement of hardware materials
Yes
Timber milling contract
Yes
Construction supervision contract
Yes
Stage2
Completed
Building pre-construction community workshop
Yes
Hardware materials delivered to site
Yes
C1.15 (d) part 11 - Construction phase environment mitigation agreed
Yes
Environment and culture protection areas identified and clearly marked
Yes
Stage3
Completed
Collect and deliver sand and gravel on site
Yes
Collect and deliver timber on site
Yes
Site clearance of proposed site
Yes
Stage4
Completed
Erection of building profiling and excavation of footings
Yes
Install reinforcement, caging and bending fro column, pad footing strip footing
No
Inspection of reinforcement for all foundations before concreting to meet TDF requirements.
No
Constructing formwork for column, pad footing and strip footing
No
Concreting of column, pad footing and strip footing
No
Stage5
Completed
Constructing of bearers structures
No
Construction of floor joist structures
No
Constructing of wall framing structures, window frame and door frame
No
Constructing of noggins, lintels and bracing of wall structures
No
Inspection of framing to meet TDF requirements
No
Stage6
Completed
Construction of roof framing and purlin structures
No
Over laid chicken mesh wire on roof structure
No
Constructing fascia board and bracing
No
Sisalation paper and roofing iron on chicken mesh
No
Inspection of roofing framing to meet TDF requirements
No
Stage7
Completed
Constructing external wall lining
No
Constructing flooring board lining
No
Construction ceiling framing structures and install lining
No
Constructing wall lining
No
Constructing of architrave
No
Stage8
Completed
Excavate septic tank and soak away pits
No
Construct septic tank with reinforcement and concrete blocks
No
Construct soak away pit with concrete and stones
No
Installation of plumbing work inside building
No
Connect water to building plumbing to septic tank
No
Stage9
Completed
Patty, filling and sand paper walls and timbers
No
Painting and decorating
No
Dismantling scaffold
No
Clean up site, remove nails and stock pile and spare materials
No
Cleaning and drainage work
No
Stage10
Completed
Building Post-Construction workshop
No
Building maintenance
No
Building service maintenance (septic & sanitation)
No
Painting and decorating maintenance
No
Landscaping and beautification of building site
No
Community procurement plan. List of up to 20 items/contracts: