Subproject Objective:
To provide better accommodation for teachers to live within the school compound.
Brief Description:
The Project will provide better accommodation for teachers and will immediately address the problem of continuous reparing of roof thatched houses every year, as well as boosting the school in terms of infrastructural area.
Date approved by Province:
04/12/2015
Date TDF approved:
20/12/2018
Community Helper name:
Emily Hillary Sausahali
Is this project added because of a discontinued project:
No
Subproject Type:
Staff Housing (Education)
Sector:
Education
Subsector:
Education nec
Date of SIC establishment meeting:
27/02/2018
Agreed name of SIC:
Haraina Kindy Staff House
SIC Executive Members:
Position (given)
Name
Gender M/F (select)
Chairperson
Joe Tara
Male
Treasurer/Accountant
Mark Waanga
Male
Secretary
Lionel Taorao
Male
Technical Officer
David Oli
Male
Youth Member
Madleen Sara
Female
Member1
Rita Matemotu
Female
Member2
Unity Ropo
Female
Member3
Robertson Waikao
Male
Total Beneficiaries
Age Group
Male
Female
Total
0 - 14 yrs
38
18
56
15 - 24 yrs
9
8
17
25 - 59 yrs
27
32
59
60+ yrs
3
4
7
Total
77
62
139
People with special needs:
0
Households:
34
Names of villages expected to benefit and number of beneficiaries:
Haraina
Age Group
Male
Female
Total
0 - 14 yrs
38
18
56
15 - 24 yrs
9
8
17
25 - 59 yrs
27
32
59
60+
3
4
7
Total
77
62
139
People with special needs
0
Households
34
Work plan stages and activities:
Stage1
Completed
Procurement/Preliminaries
Yes
Procurement of hardwares
Yes
Timber milling contract
Yes
Construction supervision contract
Yes
Stage2
Completed
C1.15d part II - Construction phase environment mitigation agreed
Yes
Environment and culture protection areas identified and clearly marked
Yes
Hardware materials delivered on site
Yes
Community Pre-construciton workshop
Yes
Stage3
Completed
Collect and deliver sand and gravel on site
Yes
Collect and deliver timber on site
Yes
Site clearance of proposed site
Yes
Building of storage shed
Yes
Stage4
Completed
Erection of building profiling and excavation of footings
Yes
Install reinforcement, caging and bending fro column, pad footing and strip footing
Yes
Inspection of reinforcement for all foundations before concreting to meet TDF requirements.
Yes
Constructing formwork for column, pad footing and strip footing
Yes
Concreting of column, pad footing and strip footing
Yes
Stage5
Completed
Constructing of bearers structures
Yes
Constructing of floor joist structures
Yes
Constructing of wall framing structures, window frame and door frame
Yes
Constructing of noggins, lintels and bracing of wall structures
Yes
Inspection of framing to meet TDF requirements
Yes
Stage6
Completed
Construction of roof framing and purlin structures
Yes
Over laid chicken mesh wire on roof structure
Yes
Constructing fascia board and bracing
Yes
Roofing iron and sisalation paper on chicken mesh
Yes
Inspection of roofing framing to meet TDF requirements
Yes
Stage7
Completed
Constructing external wall lining
Yes
Constructing of flooring board lining
Yes
Constructing ceiling framing structures and install lining
Yes
Constructing wall lining
Yes
Constructing of architrave
Yes
Stage8
Completed
Excavate septic tank and soak away pits
Yes
Construct tank with reinforcement and concrete blocks
Yes
Construct soak away pit with concrete and stones
Yes
Installation of plumbing work inside building
Yes
Connect water to building plumbing to septic tank
Yes
Stage9
Completed
Patty, filling and sand paper walls and timbers
No
Painting and decorating
No
Dismantling scaffold
No
Clean up site, remove nails and stock pile and spare materials
No
Cleaning and drainage work
No
Stage10
Completed
Building Post-Construction workshop
No
Building maintenance
No
Building service maintenance (septic & sanitation)
No
Painting and decorating maintenance
No
Landscaping and beautification of building site
No
Community procurement plan. List of up to 20 items/contracts: