Timber milling delayed due to misunderstanding by the T/CH responsible on the alteration of the roofing iron quantity which in actual fact does not alter the original design nor the whole BOQ.
29/01/2020
29/01/2020
Yes
shortfall of plumbing fittings and materials to complete the project.
26/11/2020
26/11/2020
Yes
Are Financial records being kept up to date:
Yes
Have records of community contributions been updated:
No
Are there any changes to other contributions?
No
Other Comment:
The SP has been physically completed and in use from late January 2021 by the Kindy Teacher, with only the finishing painting jobs still remaining. This is due to shortage of Lagoon Green Paints to fully complete the painting of the external walling (the SIC still need 4 tins of Lagoon Green Paints).
Records of monthly community contributions have not been updated for this period (February 2021).