Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

The objective of this programme is to improve access to basic services in rural areas
and the production and productivity of farmers.

Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

Liangai Sanitation

Print

latest report image

Status: Ongoing
50%
0%

50% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Liangai Sanitation
GPS Coordinates: -7.585394000000(lat), 156.620467000000(lng)
Province: Western
Ward: Ndovele
Village: Liangai
Cycle: Cycle3
Nature of Sub-project:

-
-
-

Subproject Objective: To provide quality water and sanitation for the community of Liangai.

Brief Description: Liangai village is located in ward 9 on the island of Vella La Vella, about 60 kilometers north of Gizo Island. It has a population of about 280 people living along the coastal lines and in land at the hill top. Liangai village suffers the effect of the recent Tsunami in 2007 which damages its water supply system built in the 1980s. The community therefore, request assistance to rehabilitate their water system and construct sanitation for the community.

Date approved by Province: 30/06/2014
Date TDF approved: 22/01/2014
Community Helper name: Dosael Glennon

Is this project added because of a discontinued project: No

Subproject Type: Sanitation
Sector: Environmental Protection
Subsector: Waste Management

Date of SIC establishment meeting: 15/12/2014
Agreed name of SIC: Lianai Sanitation

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson Elroy Jonah Male
Treasurer/Accountant Marsden Viga Male
Secretary Gillis Manovaki Male
Technical Officer Ken Patovaiki Male
Youth Member
Member1
Member2
Member3

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 42 41 83
15 - 24 yrs 18 21 39
25 - 59 yrs 66 67 133
60+ yrs 7 2 9
Total 133 131 264
People with special needs: 2 Households: 46


Names of villages expected to benefit and number of beneficiaries:

Liangai

Age Group Male Female Total
0 - 14 yrs 42 41 83
15 - 24 yrs 18 21 39
25 - 59 yrs 66 67 133
60+ 7 2 9
Total 133 131 264
People with special needs 2 Households 46

Work plan stages and activities:

Stage1 Completed
All environmental mitigation measures are followed and done Yes
Mobilisation and procurement of materials, labour, equip, etc Yes
Building orientation, profiling, squaring and leveling; timber milling and transportation to site Yes
Site clearance and development Yes
Excavation of footings Yes
Stage2 Completed
Block work to tank basement Yes
Construction of foundation (setting steel work, concrete cast in situ to footings and catchment posts Yes
Steel setting in floor slab, formwork, and concrete cast in situ to slab Yes
Stage3 Completed
Fixing up roof bracings and cyclone stripping No
Construction of roof(fixing up lintel beams, rafters, purlins, fascia and barge board No
Roof cladding and fixing up barge roll flashing No
Stage4 Completed
Fixing up gutters , storm water down pipes and connect to water tank No
Connecting reticulation lines valves and stand pipes No
Clearing and chart away all rubbish to the designated dump site No
Others if any No
All works are completed and ready for completion ceremony No

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan:

Operation and Maintenance Monitoring Report: