Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

The objective of this programme is to improve access to basic services in rural areas
and the production and productivity of farmers.

Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

Babaghea Kinder Garten

Print

latest report image

Status: Ongoing
58.8%
0%

58.8% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Babaghea Kinder Garten
GPS Coordinates: -8.011566667000(lat), 156.580683300000(lng)
Province: Western
Ward: Central ranongga
Village: Babaghea
Cycle: Cycle4
Nature of Sub-project:

-
-
-

Subproject Objective: To provide a proper venue for early childhood education for children.

Brief Description: Babaghea is a small village. It is one of the serveral small villages that sends their kids to Pienuna Community High School that includes a primary school. It is about half an hour of bush walk to Pienuna. A kindergarten facility in Babaghea would also benefit another neighboring village. It would therefore be great benefit to the children to have an early childhood classroom in place a t Babaghea.

Date approved by Province: 06/01/2014
Date TDF approved: 06/01/2014
Community Helper name: Grinta George

Is this project added because of a discontinued project: No

Subproject Type: Classroom
Sector: Education
Subsector: Pre-primary Education

Date of SIC establishment meeting: 05/02/2016
Agreed name of SIC: Babaghea Kindergarten Committee

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson Hugo Sogakolo Male
Treasurer/Accountant David Langono Male
Secretary Bernard Matua Male
Technical Officer William Paekolo Male
Youth Member
Member1
Member2
Member3

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 30 35 65
15 - 24 yrs 29 38 67
25 - 59 yrs 77 64 141
60+ yrs 5 4 9
Total 141 141 282
People with special needs: 16 Households: 54


Names of villages expected to benefit and number of beneficiaries:

Babaghea

Age Group Male Female Total
0 - 14 yrs 30 35 65
15 - 24 yrs 25 35 60
25 - 59 yrs 39 37 76
60+ 5 4 9
Total 99 111 210
People with special needs 16 Households 32

Baghu

Age Group Male Female Total
0 - 14 yrs 0 0 0
15 - 24 yrs 3 3 6
25 - 59 yrs 17 14 31
60+ 0 0 0
Total 20 17 37
People with special needs 0 Households 7

Varovo

Age Group Male Female Total
0 - 14 yrs 0 0 0
15 - 24 yrs 1 0 1
25 - 59 yrs 21 13 34
60+ 0 0 0
Total 22 13 35
People with special needs 0 Households 15

Work plan stages and activities:

Stage1 Completed
All environmental mitigation measures are followed and done Yes
Mobilization and procurement of materials, labor, equip, etc Yes
Site development and construction of storage shed Yes
Timber milling & transportation to the site Yes
Excavation of footings, building orientation, profiling, squaring and levelling Yes
Stage2 Completed
Construction of floor (excavation of strip footings, reinforcement bending and setting and concrete cast in situ to post, fixing up bearers and floor joists) Yes
Construction of wall structure and framing (fixing up bottom plates, studs and top plates) Yes
Stage3 Completed
Roof cladding and fixing up ridge capping and barge roll (insulation & wire netting) Yes
Exterior cladding and flooring Yes
Construction of roof (fixing up rafters, purling, fascia barge boards, insulation, roof bracing and cyclone strapping) Yes
Stage4 Completed
Fixing up of doors, windows, etc No
Construction of ceiling (fixing up, ceiling noggins and lining No
Internal lining No
Stage5 Completed
Painting and final touches No
Others if any No
Cleaning and chart away all rubbish to the designated dump site No
All works are completed and ready for completion ceremony No

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan:

Operation and Maintenance Monitoring Report: