Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

The objective of this programme is to improve access to basic services in rural areas
and the production and productivity of farmers.

Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

Heraniesi School Classroom

Print

latest report image

Status: Completed
90.9%
9.1%

100% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Heraniesi School Classroom
GPS Coordinates: -9.515404938734(lat), 161.4883413496(lng)
Province: Malaita
Ward: Aba/asimeuru
Village: Heraniesi
Cycle: Cycle6
Nature of Sub-project: New

-
-
-

Subproject Objective: To provide better and safe learning environment for learning to kindy and junior classes.

Brief Description: The proposed classroom building should accommodate 3 partitioned rooms to accommodate 3 separate classes. It will be a permanent structure of roofing iron and timber structure.

Date approved by Province: 24/06/2018
Date TDF approved: 14/12/2018
Community Helper name: Christian Manly Suli

Is this project added because of a discontinued project: No

Subproject Type: Classroom
Sector: Education
Subsector: Pre-primary Education

Date of SIC establishment meeting: 25/03/2018
Agreed name of SIC: Heraniesi SIC

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson Peter Saru Male
Treasurer/Accountant Joyce Teau Female
Secretary Enly Mae Male
Technical Officer Augustine Wate Male
Youth Member Reginal Sanau Male
Member1 Henry Hali Male
Member2 Florence Aitoro Female
Member3 David Saru Male

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 30 23 53
15 - 24 yrs 16 13 29
25 - 59 yrs 25 32 57
60+ yrs 5 6 11
Total 76 74 150
People with special needs: 4 Households: 37


Names of villages expected to benefit and number of beneficiaries:

Heraniesi

Age Group Male Female Total
0 - 14 yrs 30 23 53
15 - 24 yrs 16 13 29
25 - 59 yrs 25 32 57
60+ 5 6 11
Total 76 74 150
People with special needs 4 Households 37

Work plan stages and activities:

Stage1 Completed
Pre-phase construction Yes
Site clearance Yes
Sand & Gravel collection to site Yes
Timber milling and handling Yes
Stage2 Completed
Procurement of hardware materials Yes
Stage3 Completed
Profiling and foundation work Yes
Stage4 Completed
Column, filling, skeleton and roof Yes
Stage5 Completed
Wall block structure and plastering Yes
Stage6 Completed
Painting and finishing and disposals Yes
Plumbing work Yes
Completion ceremony Yes

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $
1 Timber milling Unknown Work 0
2 Hardware Materials Unknown Goods 131141
3 Contractor supervisor Unknown Services 20000
4 Plumbing supervisor Unknown Services 5000

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan:

Operation and Maintenance Monitoring Report: