No Implementation Problems or Procurement Issues Reported
Are Financial records being kept up to date:
Yes
Have records of community contributions been updated:
Yes
Are there any changes to other contributions?
No
Other Comment:
WORK STARTED ON THE 6 OF MAY 2020. FIRST STAGE ACTIVITIES ARE SEEN AS IN THE PHOTOS. HOPING THAT FOUNDATION WORK WILL SOON
Note, that not all timbers sizes are on site, number of timber counted as on site is 710, still need 200 more pieces to be load and unloaded at the site.
Brick making is progressing as well, hope the moment of work will continue over the weeks.