Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

The objective of this programme is to improve access to basic services in rural areas
and the production and productivity of farmers.

Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

Chichinge Water Supply

Print

latest report image

Status: Ongoing
0%
73.7%

73.7% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Chichinge Water Supply
GPS Coordinates: -9.49142112503(lat), 160.07430053(lng)
Province: Guadalcanal
Ward: Malango
Village: Chichinge
Cycle: Cycle6
Nature of Sub-project: New

-
-
-

Subproject Objective: To construct quality and safe drinking Water Supply for community and good living environment.

Brief Description: To construct permanent quality and safe drinking Water Supply that will cater for people's health. Communities prepare to contribute with land, materials, gravel & sand, trees for timber, labors & food..etc. Require assistant from RDP funding is to support with imported materials, tools and to assist with technical skills and construct the Bore Hole Water Supply.

Date approved by Province: 24/09/2018
Date TDF approved: 14/03/2019
Community Helper name: Betsy Hadosaia

Is this project added because of a discontinued project: No

Subproject Type: Water Supply (Borehole Gravity Fed)
Sector: Health
Subsector: Water Supply

Date of SIC establishment meeting: 22/11/2017
Agreed name of SIC: Chichinge Water Supply

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson Grace Texis Female
Treasurer/Accountant James Lee Douglus Male
Secretary Jemina Ben Female
Technical Officer Tony Piri Male
Youth Member Tabitha Tiffany Female
Member1 Philip Henry Male
Member2
Member3

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 174 188 362
15 - 24 yrs 132 170 302
25 - 59 yrs 198 209 407
60+ yrs 39 23 62
Total 543 590 1133
People with special needs: 16 Households: 261


Names of villages expected to benefit and number of beneficiaries:

Chichinge

Age Group Male Female Total
0 - 14 yrs 29 35 64
15 - 24 yrs 32 36 68
25 - 59 yrs 34 36 70
60+ 7 3 10
Total 102 110 212
People with special needs 5 Households 73

Mataruka 1

Age Group Male Female Total
0 - 14 yrs 76 63 139
15 - 24 yrs 14 45 59
25 - 59 yrs 75 75 150
60+ 8 8 16
Total 173 191 364
People with special needs 8 Households 66

Namoraoni

Age Group Male Female Total
0 - 14 yrs 19 10 29
15 - 24 yrs 16 29 45
25 - 59 yrs 29 28 57
60+ 4 2 6
Total 68 69 137
People with special needs 3 Households 22

Mataruka 2

Age Group Male Female Total
0 - 14 yrs 50 80 130
15 - 24 yrs 70 60 130
25 - 59 yrs 60 70 130
60+ 20 10 30
Total 200 220 420
People with special needs 0 Households 100

Work plan stages and activities:

Stage1 Completed
Pre-Construction Workshop Yes
Identify construction supervisor Yes
Collect sand & gravel Yes
Milling of timber Yes
Stage2 Completed
Purchase Hardware materials Yes
Purchase fuel pump & spares Yes
Transport hardware materials to village Yes
Stage3 Completed
Construct tank stands and install tank Yes
Confirm location and drill borehole Yes
Mark and brushes pipelines Yes
Stage4 Completed
Construct storage tank Yes
Construct pump shed Yes
Construct stand pipes + panels + lay pipes Yes
Excavate pipeline Yes
Stage5 Completed
Test system for leaks No
Bury pipelines No
Operation & Maintenance training No
Hygiene promotion No
Sanitation promotion No

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $
1 Mobilization Unknown Work 1850
2 Contract - water supply - Mobilization Unknown Work 2500
3 Hardware Materials Unknown Goods 168150
4 Contract - Mill timber Unknown Work 2000
5 Contract - Water Supply Unknown Work 4000
6 Transport - hardware materials Unknown Services 7500
7 Transport Local materials Unknown Services 500
8 Contract - Water Supply Unknown Work 4000
9 Contract - Water supply Unknown Work 4000
10 Contract - Water Supply Unknown Work 3000
11 Contract - Water Supply - Rention Unknown Work 2500

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan:

Operation and Maintenance Monitoring Report: