Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

The objective of this programme is to improve access to basic services in rural areas
and the production and productivity of farmers.

Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

Mbinu Kindy Classroom

Print

latest report image

Status: Ongoing
0%
40%

40% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Mbinu Kindy Classroom
GPS Coordinates: -9.466390214(lat), 160.22838277(lng)
Province: Guadalcanal
Ward: Ghaobata
Village: Mbinu
Cycle: Cycle6
Nature of Sub-project: New

-
-
-

Subproject Objective: To construct a permanent kindy classroom for children. This will provide teachers and students to learn at a good and comfortable environment to increase in human resources for our country.

Brief Description: To construct a permanent Kindy Class for conclusive and better learning environment for our young children for Mbinu and catchment area. The community is well prepared to contribute local materials like gravel, sand, trees for timber and unskilled labors. Our community required RDP for funding support in terms of hardware materials, skilled labor & technical experts to complete the project.

Date approved by Province: 24/09/2018
Date TDF approved: 12/11/2018
Community Helper name: Peter Preston

Is this project added because of a discontinued project: No

Subproject Type: Classroom
Sector: Education
Subsector: Pre-primary Education

Date of SIC establishment meeting: 05/03/2018
Agreed name of SIC: Binu Kindy Classroom SIC

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson Alfred Victor Sango Male
Treasurer/Accountant Helina Leuia Female
Secretary Lorisah Sanga Female
Technical Officer Thomas Cheka Male
Youth Member Clay Junior Sango Male
Member1 Margaret Kuvau Female
Member2 Dalsy Peresin Female
Member3 Timothy Vuria Male

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 133 118 251
15 - 24 yrs 58 64 122
25 - 59 yrs 110 109 219
60+ yrs 7 5 12
Total 308 296 604
People with special needs: 8 Households: 90


Names of villages expected to benefit and number of beneficiaries:

Mbinu

Age Group Male Female Total
0 - 14 yrs 33 37 70
15 - 24 yrs 20 28 48
25 - 59 yrs 31 27 58
60+ 2 0 2
Total 86 92 178
People with special needs 2 Households 35

Roghavolo

Age Group Male Female Total
0 - 14 yrs 31 25 56
15 - 24 yrs 13 13 26
25 - 59 yrs 35 32 67
60+ 1 1 2
Total 80 71 151
People with special needs 0 Households 24

Roroni

Age Group Male Female Total
0 - 14 yrs 69 56 125
15 - 24 yrs 25 23 48
25 - 59 yrs 44 50 94
60+ 4 4 8
Total 142 133 275
People with special needs 6 Households 31

Work plan stages and activities:

Stage1 Completed
Site development and construction of storage shed Yes
Collect sand & gravel Yes
Timber milling & timber carrying Yes
Procurement of hardware materials & transportation Yes
Profiling & excavation of trenches & footing Yes
Stage2 Completed
Concrete slabbing and block laying Yes
Block laying & septic concrete flooring & excavation No
Construction of roofing framing No
Roof cladding and ridge capping and fascia boards fixing No
Ceiling noggin and lining No
Stage3 Completed
Construction of window frame & toilet piping No
Painting and finishing No
Cleaning and land scaping No
Others if any No
100% of RDP funds acquitted by SIC and sent to PCU for audit No

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $
1 Building Supervisor (10%) Unknown Work 1700
2 Milling Unknown Work 8000
3 Mobilization Unknown Work 26730
4 Hardware Materials Unknown Goods 128390
5 Building Supervisor (40%) Unknown Work 6800
6 Hardware Materials Unknown Goods 19880
7 Building Supervisor (40%) Unknown Work 6800
8 Building Supervisor (10%) Unknown Work 1700

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan:

Operation and Maintenance Monitoring Report: