Onevemola Water Supply

Print

latest report image

Status: Approved
25.8%
0%

25.8% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Onevemola Water Supply
GPS Coordinates: -8.1525299365(lat), 156.6110997162(lng)
Province: Western
Ward: South ranongga
Village: Onevemola
Cycle: Cycle6
Nature of Sub-project: New

-
-
-

Subproject Objective: To provide accessibility to quality and reliable water-supply system for Onevemola Community.

Brief Description: The water supply is to be a gravity fed system. Sourced from the upstream of a running river and piped to stand taps right throughout the village. Onevemola is an isolated community situated above very high coral limestone cliffs along the southern coast of Ranogga Island. Accessibility to fresh water has no been easy for the Community. They have to walk down rocky steeps to fetch water then climb up back to the Village. Women, children and especially the elderly are the ones most affected living through such situation. The proposed water supply SP will certainly be of great help to them, their community and neighboring communities transiting through the village.

Date approved by Province: 19/03/2019
Date TDF approved: 16/07/2019
Community Helper name: Mcline Apusae

Is this project added because of a discontinued project: No

Subproject Type: Water Supply (Gravity Fed)
Sector: Health
Subsector: Water Supply

Date of SIC establishment meeting: 28/02/2018
Agreed name of SIC: Onevemola Water Supply

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson Nason Beikera Male
Treasurer/Accountant Joylyn Beck Female
Secretary Erick Make Male
Technical Officer Allan Niolo Male
Youth Member Annie Beck Female
Member1 Milton Agili Male
Member2 Frank Cedi Male
Member3 Emmy Beck Male

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 138 170 308
15 - 24 yrs 146 143 289
25 - 59 yrs 283 288 571
60+ yrs 67 52 119
Total 634 653 1287
People with special needs: 20 Households: 246


Names of villages expected to benefit and number of beneficiaries:

Onevemola

Age Group Male Female Total
0 - 14 yrs 19 13 32
15 - 24 yrs 6 5 11
25 - 59 yrs 87 85 172
60+ 2 3 5
Total 114 106 220
People with special needs 2 Households 27

Koqu

Age Group Male Female Total
0 - 14 yrs 41 45 86
15 - 24 yrs 39 46 85
25 - 59 yrs 69 72 141
60+ 20 18 38
Total 169 181 350
People with special needs 3 Households 67

Lale

Age Group Male Female Total
0 - 14 yrs 78 112 190
15 - 24 yrs 101 92 193
25 - 59 yrs 127 131 258
60+ 45 31 76
Total 351 366 717
People with special needs 15 Households 152

Work plan stages and activities:

Stage1 Completed
Procurement of Hardware Materials No
Timber milling contract Yes
Construction supervision contract Yes
Stage2 Completed
Pre-construction community workshop Yes
Hardware materials delivered to site No
C1.15 (d) part 11 - Construction phase environment mitigation agreed Yes
Pipe routes, environment and culture protection areas identified and clearly marked No
Tap stand locations identified to ensure equal accessibility (including women, PWD and children) No
Stage3 Completed
Collect and deliver sand + gravel, stockpiles covered Yes
Collect and deliver timber, stockpiles covered Yes
Clearance of pipe Route, Erosion Control measures implemented No
Clearance or groundwork for other sites, Erosion Control measures implemented Yes
Stage4 Completed
Construct Dam/Springbox, Environment + safety controls implemented No
Construct Ferro-cement Tank, Environment + safety controls implemented Yes
Construct 11 stand pipes, Environment + safety controls implemented No
Stage5 Completed
Environment + safety controls implemented No
Excavation of pipe trench from dam to storage tank No
Installation of pipework from dam to storage tank No
Excavation of pipe trench from storage tank to standpipes No
Installation of pipework from storage tank to standpipes No
Stage6 Completed
Pipe leakage testing No
Water quality testing No
Back fill of all pipe trenches No
Facilities equally accessible and user friendly (Children + PWD) No
Pump installed (Where applicable) No
Stage7 Completed
Drainage complete No
Re-vegetation, replanting and beautification No
Proper disposal of waste soil, materials and temporary protections No
Stage8 Completed
RWASH post-construction workshop No
System caretaker training No
Tap stand caretaker training No

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $
1 Timber milling Unknown Services 634
2 Transport & Logistics Unknown Services 2000
3 Administration Unknown Goods 350
4 Hardware Materials & Tools Unknown Goods 137302.57
5 Tools Unknown Goods 5155
6 Freights Unknown Services 34558.43
7 Labor Unknown Services 20000

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan:

Operation and Maintenance Monitoring Report: