Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

The objective of this programme is to improve access to basic services in rural areas
and the production and productivity of farmers.

Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

Popoheo Kindy Classroom

Print

latest report image

Status: Ongoing
89.1%
4.3%

93.5% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Popoheo Kindy Classroom
GPS Coordinates: -8.119665(lat), 159.532609(lng)
Province: Isabel
Ward: Hovikoilo
Village: Popoheo
Cycle: Cycle6
Nature of Sub-project: New

-
-
-

Subproject Objective: To build a proper and permanent Kindergarten classroom building which will provide a conducive environment for quality teaching and learning.

Brief Description: Early Child Hood Education is an important stage to pupil's development in learning and Growth. Without this stage of pre-learning Teacher and children will find teaching and learning difficulty at the later stages of education system. This project will help community of Popoheo to build a kindergarten classroom building conducive for better and quality teaching and learning. The classroom building is designed to accommodate more than 50 children and also the growing number o children int he future. The building will include two toilet blocks, an office and three separate classroom blocks.

Date approved by Province: 23/10/2019
Date TDF approved: 27/01/2019
Community Helper name: Selwyn Getu

Is this project added because of a discontinued project: No

Subproject Type: Classroom
Sector: Education
Subsector: Pre-primary Education

Date of SIC establishment meeting: 08/03/2018
Agreed name of SIC: Popoheo Kindergarten

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson John Neds Male
Treasurer/Accountant Francise Sasapiro Male
Secretary Moffet Ohigita Male
Technical Officer Jasper Watty Male
Youth Member Rinnah Watty Female
Member1 Pamela Gaseloku Female
Member2 Charles Sauboso Male
Member3 Jalan Naika Female

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 22 26 48
15 - 24 yrs 29 27 56
25 - 59 yrs 54 70 124
60+ yrs 6 7 13
Total 111 130 241
People with special needs: 3 Households: 28


Names of villages expected to benefit and number of beneficiaries:

Popoheo

Age Group Male Female Total
0 - 14 yrs 22 26 48
15 - 24 yrs 29 27 56
25 - 59 yrs 54 70 124
60+ 6 7 13
Total 111 130 241
People with special needs 3 Households 28

Work plan stages and activities:

Stage1 Completed
Procurement/Preliminaries Yes
Procurement of hardware materials Yes
Timber milling contract Yes
Construction supervision contract Yes
Stage2 Completed
Building pre-construction community workshop Yes
Transport of hardware materials to village Yes
C1.15 (d) part 11 - Construction phase environment mitigation agreed Yes
Environment and culture protection areas identified and clearly marked Yes
Stage3 Completed
Collect and deliver sand and gravel on site Yes
Collect and deliver timber on site Yes
Site clearance of proposed site Yes
Stage4 Completed
Erection of building profiling and excavation of footings Yes
Install reinforcement, caging and bending fro column, pad footing strip footing Yes
Inspection of reinforcement for all foundations before concreting to meet TDF requirements. Yes
Constructing formwork for column, pad footing and strip footing Yes
Concreting of column, pad footing and strip footing Yes
Stage5 Completed
Constructing of bearers structures Yes
Construction of floor joist structures Yes
Constructing of wall framing structures, window frame and door frame Yes
Constructing of noggins, lintels and bracing of wall structures Yes
Inspection of framing to meet TDF requirements Yes
Stage6 Completed
Construction of roof framing and purlin structures Yes
Over laid chicken mesh wire on roof structure Yes
Constructing fascia board and bracing Yes
Sisalation paper and roofing iron on chicken mesh Yes
Inspection of roofing framing to meet TDF requirements Yes
Stage7 Completed
Constructing external wall lining Yes
Constructing flooring board lining Yes
Construction ceiling framing structures and install lining Yes
Constructing wall lining Yes
Constructing of architrave Yes
Stage8 Completed
Excavate septic tank and soak away pits Yes
Construct tank with reinforcement and concrete blocks Yes
Construct soak away pit with concrete and stones Yes
Installation of plumbing work inside building Yes
Connect water to building plumbing to septic tank Yes
Stage9 Completed
Patty, filling and sand paper walls and timbers Yes
Painting and decorating Yes
Dismantling scaffold Yes
Clean up site, remove nails and stock pile and spare materials Yes
Cleaning and drainage work Yes
Stage10 Completed
Building Post-Construction workshop No
Building maintenance No
Building service maintenance (septic & sanitation) No
Painting and decorating maintenance Yes
Landscaping and beautification of building site Yes

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $
1 Purchase of hardware materials Unknown Goods 111429
2 Milling of Timbers Unknown Work 29973
3 Transport of hardware materials Unknown Services 30000
4 Construction supervision Unknown Work 28598

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan:

Operation and Maintenance Monitoring Report: