Solomon Islands Ministry of Development, Planning and Aid Coordination
<% completition_percent %>% Completion
<% work_stage.stage %> | Completed |
---|---|
<% work_activity.description %> |
|
Issue | Date Created | Date Updated | Resolved Y/N |
---|---|---|---|
works slowly progress | 27/11/2019 | 17/04/2020 | Yes |
The Out standing materials 1×9ft ridge cap5×50mm joint elbow1×100mm T-joint3diamond gradeth3shr rosshes2×100×50mm red bush2×50mm vent cowl1×100mm junction2×100×88mm bend3×15mm stop tap1ctn 4" JH nail | 25/07/2020 | 24/08/2020 | No |
Timber milling still continue for ceilling,wallings,window frames and door frames. | 25/08/2020 | 24/08/2020 | No |
Works slowly progress | 25/08/2020 | 25/08/2020 | No |
Missed place of CHQ book account delays the completion of the project. | 21/12/2020 | 21/12/2020 | No |