Aorigi School Staff House

Print

latest report image

Status: Completed
100%
0%

100% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Aorigi School Staff House
GPS Coordinates: -10.888697577(lat), 162.441825809(lng)
Province: Makira/Ulawa
Ward: Santa catalina
Village: Santa Catalina
Cycle: Cycle6
Nature of Sub-project: New

-
-
-

Subproject Objective: To build a permanent staff house building for teacher's accommodation.

Brief Description: This is a permanent staff house building to accommodate teachers. The building will be 6200 long x 5050 in width - two bedrooms & a living room - a shower, toilet block and small veranda.

Date approved by Province: 04/12/2015
Date TDF approved: 20/12/2018
Community Helper name: Fox Wapira

Is this project added because of a discontinued project: No

Subproject Type: Staff Housing (Education)
Sector: Education
Subsector: Education nec

Date of SIC establishment meeting: 01/03/2018
Agreed name of SIC: Santa-Catalina Staff House

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson Silas Maka'a Male
Treasurer/Accountant Fr. Jack Marainia Male
Secretary Festus Marainia Male
Technical Officer Henry Waitara Male
Youth Member David Rura Male
Member1 Mark Wasuka Male
Member2 Marlon Tai Male
Member3 Floyd Taraia Male

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 237 184 421
15 - 24 yrs 90 65 155
25 - 59 yrs 166 147 313
60+ yrs 50 64 114
Total 543 460 1003
People with special needs: 12 Households: 223


Names of villages expected to benefit and number of beneficiaries:

Santa Catalina

Age Group Male Female Total
0 - 14 yrs 237 184 421
15 - 24 yrs 90 65 155
25 - 59 yrs 166 147 313
60+ 50 64 114
Total 543 460 1003
People with special needs 12 Households 223

Work plan stages and activities:

Stage1 Completed
Procurement/Preliminaries Yes
Procurement of hardware materials Yes
Timber milling contract Yes
Construction supervision contract Yes
Stage2 Completed
C1.15(d) part 11 - Construction phase environment mitigation agreed Yes
Environment and culture protection areas identified and clearly marked Yes
Hardware materials delivered on site Yes
Community Pre-construction workshop Yes
Stage3 Completed
Collect and deliver sand and gravel on site Yes
Collect and deliver timber on site Yes
Clearance of proposed site Yes
Building of storage shed Yes
Stage4 Completed
Erection of building profiling and excavation of footings Yes
Install reinforcement, caging and bending fro column, pad footing strip footing Yes
Inspection of reinforcement for all foundations before concreting to meet TDF requirements. Yes
Constructing formwork for column, pad footing and strip footing Yes
Concreting of column, pad footing and strip footing Yes
Stage5 Completed
Constructing of wall framing structures, window frame and door frame Yes
Constructing of noggins, lintels and bracing of wall structures Yes
Inspection of framing to meet TDF requirements Yes
Stage6 Completed
Construction of roof framing and purlin structures Yes
Over laid chicken mesh wire on roof structure Yes
Constructing fascia board and bracing Yes
Sisalation paper and roofing iron on chicken mesh Yes
Inspection of roofing framing to meet TDF requirements Yes
Stage7 Completed
Constructing external wall lining Yes
Constructing of flooring board lining Yes
Constructing ceiling framing structures and install lining Yes
Constructing wall lining Yes
Construction of architrave Yes
Stage8 Completed
Excavate septic tank and soak away pits Yes
Construct tank with reinforcement and concrete blocks Yes
Construct soak away pit with concrete and stones Yes
Installation of plumbing work inside building Yes
Connect water to building plumbing to septic tank Yes
Stage9 Completed
Patty, filling and sand paper walls and timbers Yes
Painting and decorating Yes
Dismantling scaffold Yes
Clean up site, remove nails and stock pile and spare materials Yes
Cleaning and drainage work Yes

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $
1 Timber milling Unknown Goods 19019
2 Hardware Materials Unknown Goods 122403
3 Freighting and sea fare Unknown Services 29578
4 Building/Plumbing contractor Unknown Work 29000

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments: