Subproject Objective:
The purpose of this project is to provide easier access to better health and medical services to our communities and surrounding areas as well as our Primary School staff.
Brief Description:
Apaoro community is made up of two separate settlements and four major communities namely Marou, Maniri, Itaniasi, Mwaniwaro and our Primary School. These six communities has to travel to their nearby clinics Aruraha in the east and Tetere in the west by outboard motor engine using 6gallon petrol - 15 Horse Power. We really need this Project. The building will have concrete slab and continue with timber structures.
Date approved by Province:
04/12/2015
Date TDF approved:
20/12/2018
Community Helper name:
Richard Purunga
Is this project added because of a discontinued project:
No
Subproject Type:
Nurse Aid post
Sector:
Health
Subsector:
Public Health Services
Date of SIC establishment meeting:
02/06/2019
Agreed name of SIC:
Apaoro Nurse Aid
SIC Executive Members:
Position (given)
Name
Gender M/F (select)
Chairperson
John Bwea
Male
Treasurer/Accountant
Everlyn Sau
Female
Secretary
Zachariah Ngara
Male
Technical Officer
Ashley Tarimae
Male
Youth Member
Member1
Member2
Member3
Total Beneficiaries
Age Group
Male
Female
Total
0 - 14 yrs
91
71
162
15 - 24 yrs
36
27
63
25 - 59 yrs
66
63
129
60+ yrs
12
8
20
Total
205
169
374
People with special needs:
2
Households:
65
Names of villages expected to benefit and number of beneficiaries:
Apaoro
Age Group
Male
Female
Total
0 - 14 yrs
91
71
162
15 - 24 yrs
36
27
63
25 - 59 yrs
66
63
129
60+
12
8
20
Total
205
169
374
People with special needs
2
Households
65
Work plan stages and activities:
Stage1
Completed
Procurement/Preliminaries
Yes
Procurement of hardware materials
Yes
Timber milling contract
Yes
Construction supervision contract
Yes
Stage2
Completed
C1.15 (d) part 11 - Construction phase environment mitigation agreed
Yes
Environment and culture protection areas identified and clearly marked
Yes
Hardware materials delivered on site
Yes
Community Pre-Construction Workshop
Yes
Stage3
Completed
Collect and deliver sand and gravel on site
Yes
Collect and deliver timber on site
Yes
Site clearance of proposed site
Yes
Building of storage shed
Yes
Stage4
Completed
Erection of building profiling and excavation of footings
Yes
Install reinforcement, caging and bending fro column, pad footing strip footing
Yes
Inspection of reinforcement for all foundations before concreting to meet TDF requirements.
Yes
Constructing formwork for column, pad footing and strip footing
Yes
Concreting of column, pad footing and strip footing
Yes
Stage5
Completed
Constructing of bearers structure
Yes
Constructing of floor joist structures
Yes
Constructing of wall framing structures, window frame and door frame
Yes
Constructing of noggins, lintels and bracing of wall structures
Yes
Inspection of roofing framing to meet TDF requirements
Yes
Stage6
Completed
Constructing external wall lining
Yes
Construction flooring board lining
Yes
Constructing ceiling framing structures and install lining
Yes
Constructing wall lining
Yes
Constructing of architrave
Yes
Stage7
Completed
Excavate septic tank and soak away pits
Yes
Construct tank with reinforcement and concrete blocks
Yes
Construct soak away pit with concrete and stones
Yes
Installation of plumbing work inside building
Yes
Connect water to building plumbing to septic tank
Yes
Stage8
Completed
Patty, filling and sand paper walls and timbers
Yes
Painting and decorating
Yes
Dismantling scaffold
Yes
Clean up site, remove nails and stock pile and spare materials
Yes
Cleaning and drainage work
Yes
Stage9
Completed
Building Post-Construction workshop
Yes
Building maintenance
Yes
Building service maintenance (septic & sanitation)
Yes
Painting and decorating maintenance
Yes
Landscaping and beautification of building site
Yes
Community procurement plan. List of up to 20 items/contracts: