Apaoro Nurse Aid Post

Print

latest report image

Status: Ongoing
88.1%
0%

88.1% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Apaoro Nurse Aid Post
GPS Coordinates: -10.53951413435(lat), 161.5211164274(lng)
Province: Makira/Ulawa
Ward: Haununu
Village: Apaoro
Cycle: Cycle6
Nature of Sub-project: New

-
-
-

Subproject Objective: The purpose of this project is to provide easier access to better health and medical services to our communities and surrounding areas as well as our Primary School staff.

Brief Description: Apaoro community is made up of two separate settlements and four major communities namely Marou, Maniri, Itaniasi, Mwaniwaro and our Primary School. These six communities has to travel to their nearby clinics Aruraha in the east and Tetere in the west by outboard motor engine using 6gallon petrol - 15 Horse Power. We really need this Project. The building will have concrete slab and continue with timber structures.

Date approved by Province: 04/12/2015
Date TDF approved: 20/12/2018
Community Helper name: Richard Purunga

Is this project added because of a discontinued project: No

Subproject Type: Nurse Aid post
Sector: Health
Subsector: Public Health Services

Date of SIC establishment meeting: 02/06/2019
Agreed name of SIC: Apaoro Nurse Aid

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson John Bwea Male
Treasurer/Accountant Everlyn Sau Female
Secretary Zachariah Ngara Male
Technical Officer Ashley Tarimae Male
Youth Member
Member1
Member2
Member3

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 91 71 162
15 - 24 yrs 36 27 63
25 - 59 yrs 66 63 129
60+ yrs 12 8 20
Total 205 169 374
People with special needs: 2 Households: 65


Names of villages expected to benefit and number of beneficiaries:

Apaoro

Age Group Male Female Total
0 - 14 yrs 91 71 162
15 - 24 yrs 36 27 63
25 - 59 yrs 66 63 129
60+ 12 8 20
Total 205 169 374
People with special needs 2 Households 65

Work plan stages and activities:

Stage1 Completed
Procurement/Preliminaries Yes
Procurement of hardware materials Yes
Timber milling contract Yes
Construction supervision contract Yes
Stage2 Completed
C1.15 (d) part 11 - Construction phase environment mitigation agreed Yes
Environment and culture protection areas identified and clearly marked Yes
Hardware materials delivered on site Yes
Community Pre-Construction Workshop Yes
Stage3 Completed
Collect and deliver sand and gravel on site Yes
Collect and deliver timber on site Yes
Site clearance of proposed site Yes
Building of storage shed Yes
Stage4 Completed
Erection of building profiling and excavation of footings Yes
Install reinforcement, caging and bending fro column, pad footing strip footing Yes
Inspection of reinforcement for all foundations before concreting to meet TDF requirements. Yes
Constructing formwork for column, pad footing and strip footing Yes
Concreting of column, pad footing and strip footing Yes
Stage5 Completed
Constructing of bearers structure Yes
Constructing of floor joist structures Yes
Constructing of wall framing structures, window frame and door frame Yes
Constructing of noggins, lintels and bracing of wall structures Yes
Inspection of roofing framing to meet TDF requirements Yes
Stage6 Completed
Constructing external wall lining Yes
Construction flooring board lining Yes
Constructing ceiling framing structures and install lining Yes
Constructing wall lining Yes
Constructing of architrave Yes
Stage7 Completed
Excavate septic tank and soak away pits Yes
Construct tank with reinforcement and concrete blocks Yes
Construct soak away pit with concrete and stones Yes
Installation of plumbing work inside building No
Connect water to building plumbing to septic tank No
Stage8 Completed
Patty, filling and sand paper walls and timbers Yes
Painting and decorating Yes
Dismantling scaffold Yes
Clean up site, remove nails and stock pile and spare materials Yes
Cleaning and drainage work Yes
Stage9 Completed
Building Post-Construction workshop Yes
Building maintenance Yes
Building service maintenance (septic & sanitation) No
Painting and decorating maintenance No
Landscaping and beautification of building site No

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $
1 Timber Milling Unknown Goods 19019
2 Hardware Materials Unknown Goods 122403
3 Freighting/handling and sea fare Unknown Services 30578
4 Building contractor/plumbing Unknown Work 28000

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan:

Operation and Maintenance Monitoring Report: