Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

The objective of this programme is to improve access to basic services in rural areas
and the production and productivity of farmers.

Rural Development Programme

Solomon Islands Ministry of Development, Planning and Aid Coordination

Salesapa Community Hall

Print

latest report image

Status: Completed
85.7%
14.3%

100% Completion

Previous progress   Last month's progress  
Previous progress   Last month's progress  
Financial data: Total - <% getTotalPayment() | currency:symbol:2 %>
<% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %>
RDP   Community   MP   MPA   Provincial Government   CRISP   RWASH   Other  

Name: Salesapa Community Hall
GPS Coordinates: -9.12011(lat), 160.35504(lng)
Province: Central
Ward: North east gela
Village: Salesapa
Cycle: Cycle4
Nature of Sub-project:

-
-
-

Subproject Objective: To build a permanent meeting hall to enhance convenient in distance for surrounding community with the ward. To secure a better and desirable meeting venue when it comes to important gathering such as workshops, training, festivities and special occasion etc.

Brief Description: To build a new permanent Hall. This infrastructure has open concrete floor area of 59 square metres at the ground floor, with toilets & shower. At the top level it accommodates important visitors and provides a sort of office like environment for community groups. Community will provide local materials and RDP the other part.

Date approved by Province: 18/04/2012
Date TDF approved: 05/10/2012
Community Helper name: Clement Roy

Is this project added because of a discontinued project: No

Subproject Type: Community Hall
Sector: Housing and Community
Subsector: Community Development

Date of SIC establishment meeting: 22/04/2012
Agreed name of SIC: Salesapa Community Hall.

SIC Executive Members:

Position (given) Name Gender M/F (select)
Chairperson John Tumu Male
Treasurer/Accountant Henry Piluniuna Male
Secretary Allen Maipile Male
Technical Officer Peter Poepoe Male
Youth Member
Member1
Member2
Member3

Total Beneficiaries

Age Group Male Female Total
0 - 14 yrs 241 210 451
15 - 24 yrs 61 65 126
25 - 59 yrs 265 257 522
60+ yrs 37 33 70
Total 604 565 1169
People with special needs: 13 Households: 254


Names of villages expected to benefit and number of beneficiaries:

Salesapa

Age Group Male Female Total
0 - 14 yrs 83 93 176
15 - 24 yrs 18 28 46
25 - 59 yrs 108 109 217
60+ 14 14 28
Total 223 244 467
People with special needs 7 Households 105

Kombe

Age Group Male Female Total
0 - 14 yrs 82 72 154
15 - 24 yrs 25 24 49
25 - 59 yrs 71 75 146
60+ 15 11 26
Total 193 182 375
People with special needs 3 Households 88

Ghole

Age Group Male Female Total
0 - 14 yrs 76 45 121
15 - 24 yrs 18 13 31
25 - 59 yrs 86 73 159
60+ 8 8 16
Total 188 139 327
People with special needs 3 Households 61

Work plan stages and activities:

Stage1 Completed
Excavation of footings Yes
Mobilize community contribution Yes
Timber milling & transportation to the site Yes
Site assesment & clearance include construction of storage shed Yes
Site orientation, profile, squaring and leveling. Procure hardware materials Yes
Stage2 Completed
Brick laying from footings to floor slab Yes
Construction of walls (fixing up plates, studs, wall bracing and cyclone hold down bolts) Yes
Reinforcement deform & casing Yes
Construction of roof (roof beams, rafters, purlin, fascias & badge, board and roof cladding) Yes
Construction of concrete post (form work steel work & concrete cast-in situ to strip fotings and floor slab). Construction of septic and soak pit ( block laying and stone filling of soak pit). Cosntruction of ceiling (fixing up, ceiling noggin and lining) Yes
Stage3 Completed
Exterior cladding and interior lining Yes
Joinery of work (fixing of doors & locks, windows, frames & louvres) Yes
All environmental mitigation measures in the plan completed Yes
All works are completed and ready for completion ceremony Yes

Community procurement plan. List of up to 20 items/contracts:

# Contract Title Contractor Select Goods/Work/Services Cost SBD $
1 Building supervisor Unknown Work 2500
2 Hardware materials Unknown Goods 118688.3
3 Hardware materials Unknown Goods 14992

Contribution:

Source Original Amount Planned in TDF Actual amount paid Source contribution % to total Purpose RDP funds acquitted
<% agreement.financial_source.name %> <% agreement.original_amount | currency:symbol:2 %> - <% agreement.sum_payment_amount | currency:symbol:2%> <% agreement.sum_payment_amount/getTotalPayment() | percentage:1 %> <% agreement.purpose %> <% (acquittal.acquitted_amount && agreement.financial_source.name == 'RDP') ? (acquittal.acquitted_amount | currency:symbol:2) : '-' %>
Total <% getTotalOriginalAmount() | currency:symbol:2 %> - <% getTotalPayment() | currency:symbol:2 %> - - -

File attachments:
Image attachments:

Subproject Progress Monitoring Reports:

SIC and Community Subproject Evaluation Form:

Operation and Maintenance Plan:

Operation and Maintenance Monitoring Report: